Document Date
Meeting Description
Document Type
Meeting Date
Page Number
523
Section 01520 - Construction Facilities and Temporary Controls Page 2 of 2
January 2021 3066.21
1.4 REMOVAL OF UTILITIES, FACILITIES AND CONTROLS
A. CONTRACTOR shall remove temporary facilities, equipment, and materials that
CONTRACTOR installed during the performance of the Contract Work.
CONTRACTOR shall restore existing and permanent facilities used during the
performance of Work to original or better condition.
PART 2 - PRODUCTS
Not used.
PART 3 - EXECUTION
Not used.
[END OF SECTION 01520]