shall expedite and coordinate the ordering and delivery of materials that must be ordered well in advance of
construction. If the Owner agrees to procure any items prior to the establishment of the Guaranteed Maximum Price,
the Owner shall procure the items on terms and conditions acceptable to the Construction Manager. Upon the
establishment of the Guaranteed Maximum Price, the Owner shall assign all contracts for these items to the
Construction Manager and the Construction Manager shall thereafter accept responsibility for them.
Finance Committee - Agenda - 11/17/2021 - P112
Init.
ARTICLE 2 CONSTRUCTION MANAGER’S RESPONSIBILITIES
Finance Committee - Agenda - 11/17/2021 - P111
tnit.
TABLE OF ARTICLES
1 GENERAL PROVISIONS
2 CONSTRUCTION MANAGER'S RESPONSIBILITIES
3 OWNER’S RESPONSIBILITIES
4 COMPENSATION AND PAYMENTS FOR PRECONSTRUCTION PHASE SERVICES
5 COMPENSATION FOR CONSTRUCTION PHASE SERVICES
6 COST OF THE WORK FOR CONSTRUCTION PHASE
7 PAYMENTS FOR CONSTRUCTION PHASE SERVICES
8 INSURANCE AND BONDS
9 DISPUTE RESOLUTION
10 TERMINATION OR SUSPENSION
11 MISCELLANEOUS PROVISIONS
12 SCOPE OF THE AGREEMENT
EXHIBIT A GUARANTEED MAXIMUM PRICE AMENDMENT
Finance Committee - Agenda - 11/17/2021 - P110
Init.
William E. Stevens
10 Harvey Road
Bedford, NH 03110
email Address: wstevens@hccnh.com
The Architect’s Designated Representative:
(Name, address and other information)
Janet Slemenda
24 Roland Street, Suite 301 Charlestown, MA 02129
Telephone Number: 617-776-6545
Email Address: JSLEMENDA@bktarchitects.com
The Owner and Construction Manager agree as follows.
Finance Committee - Agenda - 11/17/2021 - P109
Init.
MATA Document A133" - 2009
Standard Form of Agreement Between Owner a
as Constructor where the basis of payment is the Cost
Guaranteed Maximum Price
AGREEMENT made as of the Third day of May in the year 2021
(In words, indicate day, month and year.)
BETWEEN the Owner:
(Name, legal status and address)
City of Nashua New Hampshire
229 Main Street
Nashua, NH 03060
and the Construction Manager:
(Name, legal status and address)
Finance Committee - Agenda - 11/17/2021 - P108
ga) THE CITY OF NASHUA “the Gate Cy"
Office of F-conomie Development
TO: Jim Donchess, Mayor & Michael O’Brien, Chair
FROM: — Tim Cummings, Economic Development Director
Date: November 04, 2021
RE: Approval of AIA — Document A133-2009 Contract for Construction
Manager Services with Harvey Construction
The enclosed document is a contract for construction management services for anew DPW
Administrative Office Building located on land off West Hollis Street and adjacent to the Four
Hills Landfill.
Finance Committee - Agenda - 11/17/2021 - P107
Jim Donchess
Mayor e City of Nashua
To: Board of Aldermen
From: Mayor Jim Donchess
Date: November 9, 2021
Re: Contract Award in excess of $1,000,000 — Construction Management Services for new
DPW Administrative Office Building
Pursuant to NRO: § 5-74/B: E. Approval by the Finance Committee of a contract award in excess of
$1,000,000 shall be submitted to the full Board of Aldermen at its next regularly scheduled meeting
for final approval prior to award of the contract.
Finance Committee - Agenda - 11/17/2021 - P106
City of Nashua
Purchasing Department
Administrative Services Division (603) 589-3330
229 Main Street - Nashua, NH 03060 Fax (603) 594-3233
November 9, 2021
Memo #22-187
TO: Mayor Donchess
Finance Committee
SUBJECT: Construction Management Services for a new DPW Administrative Office Building in the
amount not to exceed $12,025,000 funded from 54210 Lead Hazzard Remediation
Finance Committee - Agenda - 11/17/2021 - P105
October 14, 2021
Page 2
As noted in the original fee proposal, any work that is beyond the scope of work
shall be billed as additional services either on a time and material basis or we will
make an additional proposal with a lump sum fee or not to exceed fee. In no case
will we commence any additional services without your written approval.
If there are additional services that are required by Hoyle Tanner, we will invoice
their costs plus a mark-up of 10%.