12.04 Delays within CONTRACTOR 's Contral
A. The Contract Times (or Milestones) will not be extended due to delays within the control of CONTRACTOR.
Delays attributable to and within the control of a Subcontractor or Supplier shall be deemed to be delays within the
control of CONTRACTOR.
12.05 Delays beyond OWNER's and CONTRACTOR's Control