Finance Committee - Agenda - 6/3/2020 - P128

By dnadmin on Mon, 11/07/2022 - 13:29
  • Read more about Finance Committee - Agenda - 6/3/2020 - P128

until the submitting party has delivered the written statement of its position and full documentation to the other party.
The parties shall then attempt to resclve the dispute through good faith efforts and negotiation between the OWNER
Representative and a CONTRACTOR Representative. At all times, CONTRACTOR shall carry on the work under
this contract and maintain and complete work in accordance with the requirements of the contract or determination or

Finance Committee - Agenda - 6/3/2020 - P127

By dnadmin on Mon, 11/07/2022 - 13:29
  • Read more about Finance Committee - Agenda - 6/3/2020 - P127

professional manner. CONTRACTOR shall be given an opportunity for consultation with the OWNER prior to the
effective date of the termination. CONTRACTOR may terminate the contract on 10 calendar days written notice if,
through no fault of CONTRACTOR, the OWNER fails to pay CONTRACTOR for 45 days after the date of approval
by the OWNER of any Application for Payment.

Upon receipt of notice of termination for cause, CONTRACTOR shalt:

1. Immediately discontinue work on the date and to the extent specified in the notice.

Finance Committee - Agenda - 6/3/2020 - P126

By dnadmin on Mon, 11/07/2022 - 13:29
  • Read more about Finance Committee - Agenda - 6/3/2020 - P126

14.08 Final Completion Delayed

Finance Committee - Agenda - 6/3/2020 - P125

By dnadmin on Mon, 11/07/2022 - 13:29
  • Read more about Finance Committee - Agenda - 6/3/2020 - P125

2. No occupancy or separate operation of part of the Work may occur prior to compliance with the requirements of
paragraph 5.10 regarding property insurance.

14.06 Final Inspection

Finance Committee - Agenda - 6/3/2020 - P124

By dnadmin on Mon, 11/07/2022 - 13:29
  • Read more about Finance Committee - Agenda - 6/3/2020 - P124

3. If it is subsequently determined that OWNER's refusal of payment was not justified, the amount wrongfully
withheld shall be treated as an amount due as determined by paragraph 14.02.C.1.

14.03 CONTRACTOR’S Warranty of Title

A. CONTRACTOR warrants and guarantees that title to all Work, materials, and equipment covered by any
Application for Payment, whether incorporated in the Project or not, will pass to OWNER no later than the time of
payment free and clear of all Liens.

14.04 Substantial Completion

Finance Committee - Agenda - 6/3/2020 - P123

By dnadmin on Mon, 11/07/2022 - 13:29
  • Read more about Finance Committee - Agenda - 6/3/2020 - P123

c. OWNER has been required to correct defective Work or complete Work in accordance with paragraph
13.09; or

d. ENGINEER has actual knowledge of the occurrence of any of the events enumerated in paragraph 15.02.A.

B. Applications for Payments.

1,

Finance Committee - Agenda - 6/3/2020 - P122

By dnadmin on Mon, 11/07/2022 - 13:29
  • Read more about Finance Committee - Agenda - 6/3/2020 - P122

14.02 Progress Payment

A. Review of Applications.

1. Prior to submittal of Application for Payment to OWNER (but not more often than once a month), the
CONTRACTOR shall submit the monthly progress estimate to the ENGINEER for review and approval.

Finance Committee - Agenda - 6/3/2020 - P121

By dnadmin on Mon, 11/07/2022 - 13:29
  • Read more about Finance Committee - Agenda - 6/3/2020 - P121

13.08 Acceptance of Defective Work

Finance Committee - Agenda - 6/3/2020 - P120

By dnadmin on Mon, 11/07/2022 - 13:29
  • Read more about Finance Committee - Agenda - 6/3/2020 - P120

attributable to such uncovering, exposure, observation, inspection, testing, replacement, and reconstruction. If the
parties are unable to agree as to the amount or extent thereof, CONTRACTOR may make a Claim therefore as
provided in paragraph 10.05.

13.05 OWNER May Stop the Work

Finance Committee - Agenda - 6/3/2020 - P119

By dnadmin on Mon, 11/07/2022 - 13:29
  • Read more about Finance Committee - Agenda - 6/3/2020 - P119

1. For inspections, tests, or approvals covered by paragraphs 13.03.C and 13.03.D below;

2, That costs incurred in connection with tests or inspections conducted pursuant to paragraph 13.04.B shall be
paid as provided in said paragraph 13.04.B; and

3, As otherwise specifically provided in the Contract Documents.