12.04 Delays within CONTRACTOR 's Contral
A. The Contract Times (or Milestones) will not be extended due to delays within the control of CONTRACTOR.
Delays attributable to and within the control of a Subcontractor or Supplier shall be deemed to be delays within the
control of CONTRACTOR.
12.05 Delays beyond OWNER's and CONTRACTOR's Control
A. Where CONTRACTOR is prevented from completing any part of the Work within the Contract Times (or
Milestones) due to delay beyond the control of both OWNER and CONTRACTOR, an extension of the Contract
Times (or Milestones) in an amount equal to the time lost due to such delay shall be CONTRACTOR's sole and
exclusive remedy for such delay.
12,06 Delay Damages
A. In no event shall OWNER or ENGINEER be liable to CONTRACTOR, any Subcontractor, any Supplier, or any
other person or organization, or to any surety for or employee or agent of any of them, for damages arising out of or
resulting from:
1. Delays caused by or within the control of CONTRACTOR; or
2, Delays beyond the control of both OWNER and CONTRACTOR including but not limited to fires, flood,
epidemics, abnormal weather conditions, acts of God, or acts or neglect by utility owners or other contractors
performing other work as contemplated by Article 7.
B. Nothing in this paragraph 12.06 bars a change in Contract Price pursuant to this Article 12 to compensate
CONTRACTOR due to delay, interference, or disruption directly attributable to actions or inactions of OWNER or
anyone from whom OWNER is responsible.
ARTICLE 13 - TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
13.01 Notice of Defects
A. Prompt notice of all defective Work of which OWNER or ENGINEER has actual knowledge will be given to
CONTRACTOR. All defective Work may be rejected, corrected, or accepted as provided in this Article 13.
13.02 Access to Work
A. OWNER, ENGINEER, ENGINEER'S Consultants, other representatives and personnel of OWNER, independent
testing laboratories, and governmental agencies with jurisdictional interest will have access to the Site and the Work at
reasonable times for their observation, inspecting, and testing. CONTRACTOR shall provide them proper and safe
conditions for such access and advise them of CONTRACTOR's Site safety procedures and programs so that they may
comply therewith as applicable.
13.03 Tests and Inspections
A. CONTRACTOR shall give ENGINEER timely notice of readiness of the Work for all required inspections, tests, or
approvals and shall cooperate with inspection and testing personnel to facilitate required inspections or tests,
B. OWNER shall employ and pay for the services of an independent testing laboratory to perform all inspections, tests,
or approvals required by the Contract Documents except:
GC - 42 of 53