Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Search

Search

Displaying 4641 - 4650 of 38765

Finance Committee - Agenda - 10/5/2016 - P43

By dnadmin on Mon, 11/07/2022 - 09:49
Document Date
Wed, 10/05/2016 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/05/2016 - 00:00
Page Number
43
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100520…

ARTICLE 11— RETAINAGE

1. The OWNER will retain a portion of the progress payment, each month, in accordance with
the following procedures:

a. The OWNER will establish an escrow account in the bank of the OWNER’s
choosing. The account will be established such that interest on the principal will be
paid to the CONTRACTOR. The principal will be the accumulated retainage paid
into the account by the OWNER. The principal will be held by the bank, available
only to the OWNER, until termination of the contract.

b. Until the work is 50% complete, as determined by the OWNER, retainage shall be
10% of the monthly payments claimed. The computed amount of retainage will be
deposited in the escrow account established above. .

c. After the work is 50% complete, and provided the CONTRACTOR has satisfied
the OWNER in quality and timeliness of the work, and provided further that there
is no specific cause for withholding additional retainage no further amount will be
withheld. The escrow account will remain at the same balance throughout the
remainder of the project.

2. Upon final completion and acceptance of the Work, OWNER shall hold 2% retainage

during the 1 (one) year warranty period and release it only after the project has been
accepted.

ARTICLE 12— PROTECTION OF PERSONS AND PROPERTY

1.

The CONTRACTOR shall be responsible for initiating, maintaining and supervising all
safety precautions and programs, including all those required by law in connection with
performance of the Contract. The CONTRACTOR shall promptly remedy damage and
loss to property caused in whole or in part by the CONTRACTOR, or by anyone for
whose acts the CONTRACTOR may be liable.

ARTICLE 13 - CORRECTION OF WORK

1.

The CONTRACTOR shall promptly correct Work rejected by the OWNER as failing to
conform to the requirements of the Contract Documents. The CONTRACTOR shall bear
the cost of correcting such rejected work

In addition to the CONTRACTOR’s other obligations including warranties under the
Contract, the CONTRACTOR shall, for a period of one year after Substantial Completion,
correct work not conforming to the requirements of the Contract Documents.

If the CONTRACTOR fails to correct nonconforming Work within a reasonable time, the
OWNER may correct it and the CONTRACTOR shall reimburse the OWNER for the
cost of the correction.

ARTICLE 14 — PROHIBITED INTERESTS

CONTRACTOR shall not allow any officer or employee of the OWNER to have any indirect or
direct interest in this contract or the proceeds of this contract. CONTRACTOR warrants that no
officer or employee of the OWNER has any direct or indirect interest, whether contractual, non-
contractual, financial or otherwise, in this contract or in the business of the CONTRACTOR.
CONTRACTOR also warrants that it presently has no interest and that it will not acquire any

Page 8 of 12

Page Image
Finance Committee - Agenda - 10/5/2016 - P43

Finance Committee - Agenda - 10/5/2016 - P44

By dnadmin on Mon, 11/07/2022 - 09:49
Document Date
Wed, 10/05/2016 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/05/2016 - 00:00
Page Number
44
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100520…

interest, direct or indirect, which would conflict in any manner or degree with the performance of
services required to be performed under this contract. CONTRACTOR further warrants that no
person having such an interest shall be employed in the performance of this contract. If any such
interest comes to the attention of CONTRACTOR at any time, a full and complete disclosure of
the interest shall be immediately made in writing to the OWNER. if OWNER determines that a
conflict exists and was not disclosed to the OWNER, it may terminate the contract at will or for
cause.

ARTICLE 15 — TERMINATION OF THE CONTRACT
TERMINATION, ABANDONMENT, OR SUSPENSION AT WILL
The OWNER, in its sole discretion, shall have the right to terminate, abandon, or suspend all or
part of the project and contract at will. If the OWNER chooses to terminate, abandon, or suspend
all or part of the project, it shall provide CONTRACTOR 10 day’s written notice of its intent to

do so. If all or part of the project is suspended for more than 90 days, the suspension shall be
treated as a termination at will of all or that part of the project and contract.

Upon receipt of notice of termination, abandonment, or suspension at will, CONTRACTOR shall:

a. Immediately discontinue work on the date and to the extent specified in the notice.
b. Provide the OWNER with a list of all unperformed services.
c. Place no further orders or sub-contracts for materials, services, or facilities, other

than as may be necessary or required for completion of such portion of work under
the contract that is not terminated.

d. Immediately make every reasonable effort to obtain cancellation upon terms
satisfactory to the OWNER of all orders or sub contracts to the extent they relate to
the performance of work terminated, abandoned, or suspended under the notice,
assign to the OWNER any orders or sub contracts specified in the notice, and
revoke agreements specified in the notice.

e. Not resume work after the effective date of a notice of suspension until receipt of a
written notice from the OWNER to resume performance.

In the event of a termination, abandonment, or suspension at will, CONTRACTOR shall receive
all amounts due and not previously paid to CONTRACTOR for work satisfactorily completed in
accordance with the contract prior to the date of the notice and compensation for work thereafter
completed as specified in the notice. No amount shall be allowed or paid for anticipated profit on
unperformed services or other unperformed work.

TERMINATION FOR CAUSE

This agreement may be terminated by the OWNER on 10 calendar day’s written notice to
CONTRACTOR in the event of a failure by CONTRACTOR to adhere to any or all the terms
and conditions of the contract or for failure to satisfactorily, in the sole opinion of the OWNER, to
complete or make sufficient progress on the work in a timely and professional manner.
CONTRACTOR shall be given an opportunity for consultation with the OWNER prior to the
effective date of the termination. CONTRACTOR may terminate the contract on 10 calendar
days written notice if, through no fault of CONTRACTOR, the OWNER fails to pay
CONTRACTOR for 45 days after the date of approval by the OWNER of any Application for
Payment.

Page 9 of 12

Page Image
Finance Committee - Agenda - 10/5/2016 - P44

Finance Committee - Agenda - 10/5/2016 - P45

By dnadmin on Mon, 11/07/2022 - 09:49
Document Date
Wed, 10/05/2016 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/05/2016 - 00:00
Page Number
45
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100520…

Upon receipt of notice of termination for cause, CONTRACTOR shall:

Immediately discontinue work on the date and to the extent specified in the notice.

Provide the GWNER with a list of all unperformed services.

Place no further orders or sub-contracts for materials, services, or facilities, other than as

may be necessary or required for completion of such portion of work under the contract

that is not terminated.

4. Immediately make every reasonable effort to obtain cancellation upon terms satisfactory to
the OWNER of all orders or sub contracts to the extent they relate to the performance of
work terminated, abandoned, or suspended under the notice, assign to the OWNER any
orders or sub contracts specified in the notice, and revoke agreements specified in the
notice.

5. Not resume work after the effective date of a notice of termination unless and until receipt

of a written notice from the OWNER to resume performance.

WN eR

In the event of a termination for cause, CONTRACTOR shall receive all amounts due and not
previously paid to CONTRACTOR for work satisfactorily completed in accordance with the
contract prior to the date of the notice, less all previous payments. No amount shall be allowed or
paid for anticipated profit on unperformed services or other unperformed work. Any such payment
may be adjusted to the extent of any additional costs occasioned to the OWNER by reasons of
CONTRACTOR's failure. CONTRACTOR shall not be relieved of liability to the OWNER for
damages sustained from the failure, and the OWNER may withhold any payment to the
CONTRACTOR until such time as the exact amount of damages due to the OWNER is
determined. All claims for payment by the CONTRACTOR must be submitted to the OWNER
within 30 days of the effective date of the notice of termination.

If after termination for the failure of CONTRACTOR to adhere to any of the terms and conditions
of the contract or for failure to satisfactorily, in the sole opinion of the OWNER, to complete or
make sufficient progress on the work in a timely and professional manner, it is determined that
CONTRACTOR had not so failed, the termination shall be deemed to have been a termination at
will. In that event, the OWNER shall, if necessary, make an adjustment in the compensation paid
to CONTRACTOR such that CONTRACTOR receives total compensation in the same amount
as it would have received in the event of a termination-at-will.

GENERAL PROVISIONS FOR TERMINATION

Upon termination of the contract, the OWNER may take over the work and prosecute it to
completion by agreement with another party or otherwise. Upon termination of the contract or in
the event CONTRACTOR shall cease conducting business, the OWNER shall have the right to
solicit applications for employment from any employee of the CONTRACTOR assigned to the
performance of the contract. Neither party shall be considered in default of the performance of
such obligations is prevented or delayed by any cause, existing or future, which is beyond the
reasonable control of such party. Delays arising from the actions or inactions of one or more of
CONTRACTOR 's principals, officers, employees, agents, subcontractors, sub consultants,
vendors, or suppliers are expressly recognized to be within CONTRACTOR 's control.

Page 10 of 12

Page Image
Finance Committee - Agenda - 10/5/2016 - P45

Finance Committee - Agenda - 10/5/2016 - P46

By dnadmin on Mon, 11/07/2022 - 09:49
Document Date
Wed, 10/05/2016 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/05/2016 - 00:00
Page Number
46
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100520…

ARTICLE 16— DISPUTE RESOLUTION

The parties shall attempt to resolve any dispute related to this contract as follows. Either party
shall provide to the other party, in writing and with full documentation to verify and substantiate
its decision, its stated position concerning the dispute. No dispute shall be considered submitted
and no dispute shall be valid under this provision unless and until the submitting party has
delivered the written statement of its position and full documentation to the other party. The
parties shall then attempt to resolve the dispute through good faith efforts and negotiation between
the OWNER Representative and the CONTRACTOR Representative. At all times,
CONTRACTOR shall carry on the work under this contract and maintain and complete work in
accordance with the requirements of the contract or determination or direction of the OWNER. If
the parties are unable to resolve their dispute as described above within 30 days, the parties may
request that the dispute be submitted to the Board of Aldermen for resolution. If the parties are
dissatisfied with the decision of the Board of Aldermen, the parties’ reserve the right to pursue any
available legal and/or equitable remedies for any breaches of this contract except as that right may
be limited by the terms of this contract.

ARTICLE 17— CHOICE OF LAW AND VENUE

This contract shall be governed exclusively by the laws of the State of New Hampshire and any
claim or action brought relating to this contract, the work performed or contracted to be performed
thereunder, or referable in anyway thereto shall be brought in Hillsborough County (New
Hampshire) Superior Court Southern Judicial District or in the New Hampshire 9th Circuit
Court—Nashua and not elsewhere

ARTICLE 18— MISCELLANEOUS PROVISIONS

1. Neither party to the Contract shall assign the Contract as a whole without written consent
of the other.

2. Tests, inspections and approvals of portions of the Work required by the Contract

Documents or by laws, ordinances, rules, regulations or orders of public authorities having

jurisdiction shall be made at an appropriate time.

If additional testing is required, the CONTRACTOR shall perform these tests.

4. The OWNER shall pay for tests except for testing Work found to be defective for which
the CONTRACTOR shall pay.

ta

Page 11 of 12

Page Image
Finance Committee - Agenda - 10/5/2016 - P46

Finance Committee - Agenda - 4/20/2022 - P110

By dnadmin on Sun, 11/06/2022 - 21:43
Document Date
Fri, 04/15/2022 - 11:50
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 04/20/2022 - 00:00
Page Number
110
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__042020…

Independent Contractor, the City of Nashua fails to pay Independent Contractor for 45 days after
the date of approval by the City of Nashua of any Application for Payment.

Upon receipt of notice of termination for cause, Independent Contractor shall:

1. Immediately discontinue work on the date and to the extent specified in the notice.
. Provide the City of Nashua with a list of all unperformed services.

3. Place no further orders or sub-contracts for materials, services, or facilities, other than as
may be necessary or required for completion of such portion of work under the contract
that is not terminated.

4. Immediately make every reasonable effort to obtain cancellation upon terms satisfactory
to the City of Nashua of all orders or sub contracts to the extent they relate to the
performance of work terminated, abandoned, or suspended under the notice, assign to
the City of Nashua any orders or sub contracts specified in the notice, and revoke
agreements specified in the notice.

5. Not resume work after the effective date of a notice of termination unless and until receipt
of a written notice from the City of Nashua to resume performance.

In the event of a termination for cause, Independent Contractor shall receive all amounts due and
not previously paid to Independent Contractor for work satisfactorily completed in accordance with
the contract prior to the date of the notice, less all previous payments. No amount shall be allowed
or paid for anticipated profit on unperformed services or other unperformed work. Any such
payment may be adjusted to the extent of any additional costs occasioned to the City of Nashua by
reasons of Independent Contractor's failure. Independent Contractor shall not be relieved of liability
to the City of Nashua for damages sustained from the failure, and the City of Nashua may withhold
any payment to the Independent Contractor until such time as the exact amount of damages due to
the City of Nashua is determined. All claims for payment by the Independent Contractor must be
submitted to the City of Nashua within 30 days of the effective date of the notice of termination.

If after termination for the failure of Independent Contractor to adhere to any of the terms and
conditions of the contract or for failure to satisfactorily, in the sole opinion of the City of Nashua,
to complete or make sufficient progress on the work in a timely and professional manner, it is
determined that Independent Contractor had not so failed, the termination shall be deemed to have
been a termination at will. In that event, the City of Nashua shall, if necessary, make an adjustment
in the compensation paid to Independent Contractor such that Independent Contractor receives total
compensation in the same amount as it would have received in the event of a termination-at-will.

C. GENERAL PROVISIONS FOR TERMINATION Upon termination of the contract, the City of
Nashua may take over the work and prosecute it to completion by agreement with another party or
otherwise. In the event Independent Contractor shall cease conducting business, the City of Nashua
shall have the right to solicit applications for employment from any employee of the Independent
Contractor assigned to the performance of the contract.

Neither party shall be considered in default of the performance of its obligations hereunder to the
extent that performance of such obligations is prevented or delayed by any cause, existing or future,
which is beyond the reasonable control of such party. Delays arising from the actions or inactions
of one or more of Independent Contractor's principals, officers, employees, agents, subcontractors,
consultants, vendors, or suppliers are expressly recognized to be within Independent Contractor's
control.

DISPUTE RESOLUTION The parties shall attempt to resolve any dispute related to this contract as
follows. Either party shall provide to the other party, in writing and with full documentation to

GC-5

Page Image
Finance Committee - Agenda - 4/20/2022 - P110

Finance Committee - Agenda - 10/5/2016 - P47

By dnadmin on Mon, 11/07/2022 - 09:49
Document Date
Wed, 10/05/2016 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/05/2016 - 00:00
Page Number
47
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100520…

IN WITNESS WHEREOF, the parties hereto have caused this contract to be signed and intend to be
legally bound thereby.

City of Nashua, NH (signature) CONTRACTOR (signature)

James Donchess, Mayor
(Printed Name and Title) (Printed Name and Title)

Date Date

Page 12 of 12

Page Image
Finance Committee - Agenda - 10/5/2016 - P47

Finance Committee - Agenda - 10/5/2016 - P48

By dnadmin on Mon, 11/07/2022 - 09:49
Document Date
Wed, 10/05/2016 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/05/2016 - 00:00
Page Number
48
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100520…

) THE CITY OF NASHUA “The Gate City"

Financial Services

Purchasing Department

September 29, 2016
Memo #17-061

TO: MAYOR DONCHESS
FINANCE COMMITTEE

SUBJECT: | CHANGE ORDER #1 BROAD STREET PARKWAY BRIDGE LED LIGHTING (VALUE
$2,250)
DEPARTMENT: 181 COMMUNITY DEVELOPMENT; FUND: CAPITAL PROJECT

Please see attached communication from Sarah Marchant, Community Development Division
Director, dated September 27, 2016 for information related to this contract award.

Sarah Marchant, Director of Community Development and the Purchasing Department

recommend Change Order #1 to this contract to Port Lighting, Inc. of Seabrook, NH in the
amount of $2,250.

Respectfully,
Dan Kooken

Purchasing Manager

Ce: S. Marchant J. Graziano

229 Main Street e Nashua, New Hampshire 03061 « Phone (603) 589-3330 Fax (603) 589-3344

Page Image
Finance Committee - Agenda - 10/5/2016 - P48

Finance Committee - Agenda - 10/5/2016 - P49

By dnadmin on Mon, 11/07/2022 - 09:49
Document Date
Wed, 10/05/2016 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/05/2016 - 00:00
Page Number
49
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100520…

City of Nashua corm oeeren
Community Development Division Building Safety
City Hall, 229 Main Street, PO Box 2019 See tes partment
Nashua, New Hampshire 03061-2019 FAX

www.nashuanh.gov
To: Dan Kooken, Purchasing Manager

From: Sarah Marchant, Director of Community Development

Date: September 27, 2016

Re: Amendment to Port Lighting, Inc Professional Services Contract

589-3095
589-3090
589-3080
589-3100
589-3085
880-0100
589-3119

In June of 2016 the Finance Committee approved the award of a contract to Port Lighting, Inc in
the amount of $149,979 for the design and installation of the Broad Street Parkway River Bridge
LED Lighting contract. Funding for this project was donated by Mr. Richard Stahl in December,
2015 and accepted by the Board of Alderman via R-15-197.

The original RFP and contract did not include the requirement for the project to including
bonding. Understanding a bond is required by state law to start the project, the contractor offered
to split the bond procurement costs with the City. An amendment to the contract has been put
forward in the amount of $2250 to include half of the financing costs for procuring a bond for the
project by the contractor. Herewith, please find construction change order No. 1 which increases
the contract price by $2,250 for the added requirement of the contractor providing performance
and payment bonds as required by law.

Page Image
Finance Committee - Agenda - 10/5/2016 - P49

Finance Committee - Agenda - 10/5/2016 - P50

By dnadmin on Mon, 11/07/2022 - 09:49
Document Date
Wed, 10/05/2016 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/05/2016 - 00:00
Page Number
50
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100520…

CHANGE ORDER

No. 1
PROJECT: __ Broad Street Parkway Lighting
OWNER’S CONTRACT NO: 127871
EXECUTED CONTRACT DATE: _ July 15, 2016
DATE OF ISSUANCE: 9/27/16 EFFECTIVE DATE: Upon City Approval

OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 127871
CONTRACTOR: Lighthouse Productions Inc, DBA Port Lighting Systems

ENGINEER:

You are directed to make the following changes in the Contract Documents:

Description:

An amendment to the contract has been put forward in the amount of $2,250 to include half of the
financing costs for procuring a bond for the project by the contractor.

Justification:

The original RFP and contract did not include the requirement for the project to including bonding.
Understanding a bond is required by state law to start the project, the contractor offered to split the
bond procurement costs with the City.

Change Order # 2 1 of 2
Southwest Trails

Page Image
Finance Committee - Agenda - 10/5/2016 - P50

Finance Committee - Agenda - 10/5/2016 - P51

By dnadmin on Mon, 11/07/2022 - 09:49
Document Date
Wed, 10/05/2016 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/05/2016 - 00:00
Page Number
51
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100520…

Summary

CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times
$149,978.70 Substantial completion:
Ready for final payment:
Net changes from previous Change Orders Net change from previous Change Orders
$0.00
Contract Price prior to this Change Order Contract Times prior to this Change Order
$149,978.70 Substantial completion:
Ready for final payment:
Net Increase (decreasejof this Change Order Net Increase (deerease} of this Change Order
$2,250
Contract Price with all approved Change Orders Contract Times with all approved Change Orders
$152,228.70 Substantial completion:
Ready for final payment:
RECOMMENDED: ACCEPTED: APPROVED:
By: By By
Sarah Marchant Port Lighting Systems Mayor Jim Donchess
(Authorized Signature) (Authorized Signature) Owner
(Authorized Signature)
Date: Date:
Date:
Change Order # 2 2 of 2

Southwest Trails

Page Image
Finance Committee - Agenda - 10/5/2016 - P51

Pagination

  • First page « First
  • Previous page ‹‹
  • …
  • Page 461
  • Page 462
  • Page 463
  • Page 464
  • Current page 465
  • Page 466
  • Page 467
  • Page 468
  • Page 469
  • …
  • Next page ››
  • Last page Last »

Search

Meeting Date
Document Date

Footer menu

  • Contact