Finance Committee - Agenda - 10/2/2019 - P3

By dnadmin on Mon, 11/07/2022 - 13:03
Document Date
Fri, 09/27/2019 - 12:02
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/02/2019 - 00:00
Page Number
3
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100220…

229 Main street

I P.O, Box 2019
C ity of N as h ua Nashua, NH 03061-2019
Office of the City Clerk (603) 589-3010 Option #5
. . Fax (603) 589-3029
Susan K. Lovering Wendy Drouin E-Mail: cityclerkdept@NashuaNH.gov
City Clerk Deputy City Clerk
Memorandum
To: Dan Kooken, Purchasing
Donna Graham, Legislative Affairs P>
From: Wendy Drouin, Deputy City Clerk
Date: October 2, 2019
Re: Emergency PO Change Order Request

Attached, please find the request from Mayor Donchess for an emergency PO
change order. This has been filed here in the City Clerk's office today.

Enclosures

Page Image
Finance Committee - Agenda - 10/2/2019 - P3

Finance Committee - Agenda - 10/2/2019 - P4

By dnadmin on Mon, 11/07/2022 - 13:03
Document Date
Fri, 09/27/2019 - 12:02
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/02/2019 - 00:00
Page Number
4
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100220…

Jim Donchess
Mayor e City of Nashua

To: Board of Aldermen

Filed With: Sue Lovering, City Clerk

From: Jim Donchess
Date: October 2, 2019
Re: Emergency PO Change Order Request — Change Order 3 for Energy Recovery

Upgrade for WWTF for $10,710

Pursuant to 5-90 (G) of the NRO, | have authorized Emergency Purchase Order Change Order 3
for the Energy Recovery Upgrade for WWTF in an amount of $10,710 to Methuen Construction
Inc. of Plaistow, NH for the work required.

Included is a copy of an e-mail dated October 1, 2019 from Carolyn O'Conner,
Finance and Administration Manager to Kimberly Kleiner, Administrative Services
Director, explaining the cause and the need for this emergency work and copies
Change Order 3 documentation detailing the work needed.

Once filed with the City Clerk's office a Requisition will entered and a PO
generated that will allow these repairs to be implemented and completed as soon
as possible.

Thank you,
cc: DPW Administration

229 Main Street » PO Box 2019 * Nashua, New Hampshire 03061-2019
603.589.3260 + fax 603.594.3450 + NashuaMayor@NashuaNH.gov
www.NashuaNH.gov

Page Image
Finance Committee - Agenda - 10/2/2019 - P4

Finance Committee - Agenda - 10/2/2019 - P5

By dnadmin on Mon, 11/07/2022 - 13:03
Document Date
Fri, 09/27/2019 - 12:02
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/02/2019 - 00:00
Page Number
5
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100220…

Kooken, Daniel

From: O'Connor, Carolyn

Sent: Tuesday, October 01, 2019 4:21 PM

To: Kleiner, Kimberly

Ce: Fauteux, Lisa; Keating, William; Carragan, Kathleen; Boucher, David; Kooken, Daniel
Subject: FW: CO3 for Energy Recovery

Attachments: 20191001-CO3-signed by contractor-engineer.pdf

Importance: High

Hi Kim,

FYI, DPW ts in the process of preparing the attached Change Order for transmittal to you for the Mayor's signature. The Change Order is in the amount of
$10,710 and does not require BPW or Finance Committee approval.

This change order is the result of unknown conditions. It was unknown there would be conduit below the floor slab until the contractor removed the concrete.
The conduit needs to be relocated in order for work to continue. The project is on hold until the Change Order is approved.

Wanted you to have the background on the Change Order and be able to review with Mayor for his signature/approval ASAP.

(Mary Woods will be hand delivering the document with Transmittal sheet this afternoon.)

Please let me know if any additional information is required to complete approval.

Thank you,

Carolyn

Finance & Administration Manager

City of Nashua, New Hampshire

(P) 603.589,3135
(F) 603.589.3169

Page Image
Finance Committee - Agenda - 10/2/2019 - P5

Finance Committee - Agenda - 10/2/2019 - P6

By dnadmin on Mon, 11/07/2022 - 13:03
Document Date
Fri, 09/27/2019 - 12:02
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/02/2019 - 00:00
Page Number
6
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100220…

CHANGE ORDER

No. 3

PROJECT: _Energy Recovery Upgrade

DATE OF ISSUANCE:

OWNER: City of Nashua, NH

229 Main Street, Nashua, NH
Address)
CONTRACTOR: Methuen Construction
CONTRACT

10/1/2019

OWNER’s Project No. _IFB0501-091618

FOR: Energy Recovery Upgrade ENGINEER Waldron Eng. & Const., Inc.

ENGINEER’ Project No. 359.61

You are directed to make the following changes in the Contract Documents.

Description:
Purpose of Change Order:
Justification:

Attachments: (List documents supporting change}

CHANGE IN CONTRACT PRICE

Original Contract Price
$ 1,787,378.00

CHANGE IN CONTRACT TIME

Original Contract Time

280 (Final Completion)
(days or date}

Previous Change Orders
$ 37,923.56

Net change from previous Change Orders

hone
(days)

Contract Price prior to this Change Order
$ 1,825,301.56

Contract Time prior to this Change Order

280 (Final Completion)
(days or date}

Net Increase (Decrease) of this Change Order
$ 10,710.00

Net Increase (decrease) this Change Order

none
(days)

Contract Price with all approved Change Orders
$ _1,836,011.56

Contract Time with ali Change Orders

280 (Final Completion)
(days or date)

This document will become a supplement to the CONTRACT and all provisions will apply hereto, The
attached Contractor’s Revised Project Schedule reflects increases or decreases in Contract Time as
authorized by this Change Order.

Stipulated price and time adjustment includes all costs and time associated with the above described
change. Contractor waives all rights for additional time extension for said change. Contractor and Owner
agree that the price(s) and time adjastment(s} stated above are equitable and acceptable to both parties.

RECOMMENDED: _—-##PPROVED: APPROVED: APPROVED:
By: By: Bie ser «BY:
ST Engineer ‘Owner Conuacior NHDES
[et 19) wile
v Date Date * Date Date

Page Image
Finance Committee - Agenda - 10/2/2019 - P6

Finance Committee - Agenda - 10/2/2019 - P7

By dnadmin on Mon, 11/07/2022 - 13:03
Document Date
Fri, 09/27/2019 - 12:02
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/02/2019 - 00:00
Page Number
7
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100220…

WALORON ENGINEERING & CONSTRUCTION, INC.

To: William Keating, P.E., Project Engineer, Nashua Wastewater Treatment Facility
From: Jeremy P. Smith, P.E., Project Manager, Waldron Engineering & Construction,
Inc.
Date: October 1, 2019
Re: Change Order Request Review 007
NWWTE Energy Recovery Upgrade Project
Attachments: Methuen Construction PCO #007
WEC]I Field Report 09/30/2019
Mr. Keating:

Waldron has compiled its review based on review of the Owner's documentation (design
documents, OEM submittals, submittal reviews, RFI responses, project notes and meetings

minutes) and the Contractor’s documentation (RFI's,

Submittals, Reports, issued Change Orders).

Specifically, Waldron has reviewed the issue of additional work associated with removal and

relocation of existing electric
the locations of the new foundations for the engine support
required demo, rerouting, and rep
relocated as well as repair of any 0

al conduit that was discovered in the Energy Recovery building in
frame. The scope will include all
owering of all affected conduit that will be required to be
ther conduit that will remain which was damaged during.

cutting of interior CMU wall and slab performed either by Methuen or their subcontractor as

applicable.

Summary Review

Original Schedule Schedule Direct Schedule Schedule Claim
Adjustment claim Impact Assessment Recommended
None none wa 0 days
Original Cost Cost Adjustment Direct Cost lmpact Cost Adjustment
claim Assessment Recommended
None Nat to Exceed Not to Exceed Not to Exceed
$10,710.00 $10,710.00 $16,710.00

Detailed Review-Base Cost. Validity

Methuen has made a claim for the time and materials work not to exceed the amount stated as
described above based on review by Methuen and Waldron on site and described in the
September 30, 2019 WECTI field report. The claim is based on their work and their
subcontractor’s work resulting from the above.

Full detailed review of request was not complete due to the unknown extent of conduit and wiring

that requires replacement, Waldron request

s that once extent of work is known or following

completion of work, Methuen shall submit record of time spent and total linear feet of conduit

S7 INDUSTRIAL DRIVE SUITEG-1 EXETER, NHO3e8a3 (603)772 7153

WALDRON COM

Page Image
Finance Committee - Agenda - 10/2/2019 - P7

Finance Committee - Agenda - 10/2/2019 - P8

By dnadmin on Mon, 11/07/2022 - 13:03
Document Date
Fri, 09/27/2019 - 12:02
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/02/2019 - 00:00
Page Number
8
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100220…

and wiring used during work. Waldron will use this information to confirm cost validity of the

scope of work completed,
Detailed Review-Schedul
Methuen did not make a claim for schedule adjustment and as such no review was conducted.
Original Schedule Schedule Direct Schedule Schedule Claim
Adjustment claim impact Assessment Recommended
None none n/a 0 days
Conclusion

Waldron has reviewed all the available information, and has taken into consideration the factors
surrounding the issues in question. Waldron takes no exception to costs and schedule relief as
submitted.

Thus, Waldron recommends approving the Time and Material Not to Exceed $10,710.00 of the
claim as noted above and approving 0 days of schedule relief.

If you have any questions on the above, please don’t hesitate to contact me at 603-772-7153 x
105 or jsmith@waldron.com

Sincerely
Waldron Engineering & Construction, Inc.

Joreeey PB. Stehta

Jeremy P. Smith, P.B.
Project Manager

Page Image
Finance Committee - Agenda - 10/2/2019 - P8

Finance Committee - Agenda - 10/2/2019 - P9

By dnadmin on Mon, 11/07/2022 - 13:03
Document Date
Fri, 09/27/2019 - 12:02
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/02/2019 - 00:00
Page Number
9
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100220…

Doc #: PCO RO 007
: Ref. Document:
OJECT NAME: Date: {-Oct-19

Na

PR

Nashua Energy Rercovery Upgrade
PROJECT NO: 181012
PHASE
COST SUMMARY SHEET
TITLE
A MC Labor (Recap Sheet): $0.00 |
B MC Materials, & Equipment (Recap Sheet): $0.00
¢ MC Fes (A x 15%) + (B x 10%): $0.00 |}
D Subtotal MC Work (A+B +C): | $ -
E Total Subcontractars (Below): $10,000.00
F MC Mark-up on Subcontractor Work (5%): $ 500.00
| GS Bond (1%) and Genera! Liability (1%): $210.00
Total Proposal (D+#E+F+G): & 40,710.00

———————

SUBCONTRACTOR SUMMARY

Amount

Relocate Conduit for Gen Foundation 10,000.00

$
$
$
$
$
$
§
$

Total Subcontractors: 10,000.00

Page Image
Finance Committee - Agenda - 10/2/2019 - P9

Finance Committee - Agenda - 10/2/2019 - P10

By dnadmin on Mon, 11/07/2022 - 13:03
Document Date
Fri, 09/27/2019 - 12:02
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/02/2019 - 00:00
Page Number
10
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100220…

TITLE

Scope: The balow price ts the oust Incurred lo repalr the water seal on miker DS. The Seal was found to be damaged, and SESD asked MOIS tc repair the seal prior te
assembling the new mixer shefi. Accass was installed to the area, the ploce was preparred for welding, and welding was performed par the instructions of SESD in

rasponss to RFIOO7.
41-LABOR
CATEGORY HRS RATE/HR PREMIUM SUBTOTAL LINE TOTAL TOTAL
60
$0.00
i2-MATERIALS
DESCRIPTION QTy UNIT UNIT COST SUBTOTAL
Estimated
Consumables $ 500,00 §$ 500.00 $ -
Dumpster / Disposal + 750.00 $ 750.00 § -
| { _|
SUBTOTAL $ -
2-EQUIPMENT
CATEGORY HRS RATE UNIT SUBTOTAL
VATOR PC300
T 336
OR 320
SUBTOTAL $0,00

Page 2 of 3 10/1/2015 - 8:35 AM

Page Image
Finance Committee - Agenda - 10/2/2019 - P10

Finance Committee - Agenda - 10/2/2019 - P11

By dnadmin on Mon, 11/07/2022 - 13:03
Document Date
Fri, 09/27/2019 - 12:02
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/02/2019 - 00:00
Page Number
11
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100220…

TITLE

Seopa: The below price is the cost Incurred to repalr the water seal on mixer DS. The Seal was found to be damaged, and SESD asked MCIS to repalr the seal prior to
assembling the new mixer shefi. Accens was instellad to the grea, the pleca was preparred for welding, and welding was performed par the Instructions of SESD In

rasponse to RFIOO?.

4-SUPPLEMENTAL COSTS
DESCRIPTION ary RATE UNIT SUBTOTAL
t

SUBTOTAL $0.00

ig-BURDEN
CATEGORY RATE

BURDEN RATE 34.00% $0.00
free WORK TOTAL

SUBTOTAL (Item 1424344) $0.00
A
7-SUBCONTRACTORS WORK

SUBCONTRACTOR UNIT COST Qty COST TOTAL
to

SUBTOTAL $10,000.00
B-FEE

GO (15% X Hams 14.5 + 10% XM tems 26364 + 696 X em 7} $500.00
Is-SUBTOTAL $10,500.00

BOND {1% X Hem®) $105.00

GENERAL LIABILITY (1% X item 8) $105.00
prore. {tem 8 + Bond + Genera! Liability} $10,710.00

Page 3 0f3 10/1/2015: 8:35 AM

Page Image
Finance Committee - Agenda - 10/2/2019 - P11

Finance Committee - Agenda - 10/2/2019 - P12

By dnadmin on Mon, 11/07/2022 - 13:03
Document Date
Fri, 09/27/2019 - 12:02
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/02/2019 - 00:00
Page Number
12
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100220…

ey wi nla cre Pic | Lida ate bh Gabbe
Elected cal 397 Whittier Highway 9308 American Legion Hwy
Moultonbeora, NH 03254 Westport, MA 02790
installations. 1 Ine. 603-253-4525 568-636-9600
Tee Meclawiew, NE FAX 603-253-6284 FAX 508-636-8650

September 30, 2019

To: Don Hutchinson

Methuen Construction

Energy Recovery Project Time and (Viaterials work

Remove in slab conduit and wire located in two square holes in generator room floor for new
support post. Remove in wall conduit and wire for two support beams for new generator. Remove
two %” PVC conduits and wires for new support beam on outside wall.

Install new surface conduit and wire to replace all conduit and wire that has been removed per
demo of the above description.

This work will be fogged in on a daily sheet and a copy will be given to Methuen Construction at the
end of each day’s work.

The Time and materials work will not exceed the amount of $10,000.00

lf any additional work Is required beyond what is described above addition approval will be
requested by the City.

if you have any questions or need more information please feel free to call.

Sincerely,
Charles L. Fritz, Jr.
VWieotebgsident

GY f.

Page Image
Finance Committee - Agenda - 10/2/2019 - P12

Pagination

  • First page « First
  • Previous page ‹‹
  • …
  • Page 1853
  • Page 1854
  • Page 1855
  • Page 1856
  • Current page 1857
  • Page 1858
  • Page 1859
  • Page 1860
  • Page 1861
  • …
  • Next page ››
  • Last page Last »

Search

Meeting Date
Document Date

Footer menu

  • Contact