Finance Committee - Agenda - 3/6/2019 - P33
IFB0660-020719
ADDENDUM #2
2019 PAVING PROGRAM
ARTERIAL ROADWAYS
Addendum #2 is being issued io transmit additional information about the bid.
Deferred Strects
Seleci arterial streets have been deferred due to underground utilities conflict. The
deferred dates are listed in the attached table. These streets will be available io the
contractor once the underground utility concerns have been addressed.