Finance Committee - Agenda - 6/7/2017 - P492

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P492

01800-7
EQUIPMENT/ SYSTEM TESTING CERTIFICATION

EQUIPMENT TRAINING CERTIFICATION

Owner: Date:

Project:

Contractor:

Equipment Manufacturer:

Equipment:

1. I have trained the Owner's personnel in the proper operation and maintenance of the above
equipment.

(Authorized Representative of the Manufacturer) (Date)

2. The personnel listed below attended the training session.

(Owner's Representative) (Date)

3. Witnessed by:

Wright-Pierce (Date)
Wright-Pierce

Finance Committee - Agenda - 6/7/2017 - P491

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P491

01800-6
EQUIPMENT/ SYSTEM TESTING CERTIFICATION

EQUIPMENT START-UP CERTIFICATION

Owner: Date:

Project:

Contractor:

Equipment Manufacturer:

Equipment:

Finance Committee - Agenda - 6/7/2017 - P490

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P490

3.3

01800-5
EQUIPMENT/ SYSTEM TESTING CERTIFICATION

values representing zero percent, ten percent, and eighty percent of full scale.

3. The inputs and outputs of devices, as appropriate, shall be connected to
manometers for differential pressure devices, or compared to measured levels,
rates or quantities, during calibration. The receiving devices shall be adjusted
to read the calibrated output of the initial calibration.

Finance Committee - Agenda - 6/7/2017 - P489

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P489

01800-4
EQUIPMENT/ SYSTEM TESTING CERTIFICATION

not exceed 90 dBA, as measured 3 feet from the unit under free field

conditions.

a. Each unit shall be monitored for compliance independently with other
area equipment deactivated.

b. For monitoring, the equipment will be run under normal operation
conditions.

c. Contractor shall provide certified proof of calibration for instrument
utilized to measure noise level.

6. Other specific requirements as outlined within the individual specifications
sections.

Finance Committee - Agenda - 6/7/2017 - P488

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P488

Om

01800-3
EQUIPMENT/ SYSTEM TESTING CERTIFICATION

testing are within acceptable limits. The startup shall not be considered complete

until the unit is fully capable of passing the equipment certification testing.

Where multiple units are provided, each unit shall under go startup procedures.

The Contractor shall provide all power, chemical, tools, equipment, labor, water

fuel, coordinate with Owner to ensure availability of sludge, etc. as required for

startup.

Finance Committee - Agenda - 6/7/2017 - P487

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P487

E.

01800-2
EQUIPMENT/ SYSTEM TESTING CERTIFICATION

Schedules:

1. The Pre-Startup Meeting shall be held at least ten (10) working days prior to
the startup of the first piece of equipment supplied under the Contract. At that
time, the Contractor shall present his plan as detailed in the previous Part D
"Submittals" and review Engineer's comments and concerns associated with
the general features of each piece of equipment which must be demonstrated.

Finance Committee - Agenda - 6/7/2017 - P486

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P486

01800-1

SECTION 01800

EQUIPMENT STARTUP, CERTIFICATION AND OPERATOR TRAINING

PART 1 - GENERAL

1.1

DESCRIPTION
A. Work Included:

1.

Finance Committee - Agenda - 6/7/2017 - P485

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P485

01720-4
PROJECT RECORD DOCUMENTS

3. Title and number of each record document with certification that each
document is completed and accurate.

4. Signature of Contractor, or his authorized representative.

Failure to supply all information on the Project Record Drawings as specified in

Part 1.3 may result in additional retainage from monthly partial payment requests,

and in non-approval of final payments of the Contract and/or if contract time (as

specified in accordance with the Standard General Conditions of the Construction

Finance Committee - Agenda - 6/7/2017 - P484

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P484

01720-3
PROJECT RECORD DOCUMENTS

6. Roads

a. Show centerline road profile and level spot elevations.

b. Show pavement widths.

c. Onroad cross sections, show the pavement cross slope.

d. Show any deviations from the design plans.

7. Buildings

a. In general, small changes to structures should not be redrawn. If any
dimensional changes were made in the field, the numerical change
should be made on the Drawing and be properly labeled. Update
dimensions and elevations on Drawings.

Finance Committee - Agenda - 6/7/2017 - P483

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P483

01720-2
PROJECT RECORD DOCUMENTS

Existing Utilities

a. Water mains and services, water main gate valves, sewer mains and
services, storm drains, culverts, steam lines, gas lines, tanks and other
existing utilities encountered during construction must be accurately
located and shown on the Drawings. In congested areas supplemental
drawings or enlargements may be required.