10.

TIE-IN AT SIDE ROAD
Side road tie-in areas shall be milled to the same depth as specified for the roadway.

INTERIM MILESTONES FOR SUBSTANTIAL MPLETI
The following Substantial Completion Milestones shall be met:

50 percent of the total length of all roadways segments in the contract shall be substantial
complete by July 16, 2021.

85 percent of the total length of all roadways segments in the contract shall be substantial
complete by September 3, 2021.

Finance Committee - Agenda - 3/17/2021 - P203

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P203

4.

inch. Base and binder courses shall be 50 gyration with PG 64-28 and maximum
aggregate size of % inch.

The following course thicknesses shall be used:

1.5” Mill & Overlay
1.5” wearing course.

2” Mill & Overlay
2” wearing course.

Reclamation
1.5” wearing course over 2” binder course.

THER RKI TRACT AREA
Other City and utility work may be in progress within the project area during work in this
contract.

Finance Committee - Agenda - 3/17/2021 - P202

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P202

SUPPLEMENTARY CONDITIONS/PROSECUTION OF WORK

These Supplementary Conditions amend or supplement the Standard General Conditions of the
Construction Contract and other provisions of the Contract Documents as indicated below. All
provisions which are not so amended or supplemented remain in full force and effect.

1.

DESCRIPTION OF WORK

The contract work includes the limits on the various streets listed in the attached
summary. The specified pavement treatment is listed.

Finance Committee - Agenda - 3/17/2021 - P201

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P201

DIVISION 6

SUPPLEMENTARY CONDITIONS
PROSECUTION OF WORK

Finance Committee - Agenda - 3/17/2021 - P200

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P200

2. At least 5 days prior to the proposed closure, the CONTRACTOR shall submit a detour traffic plan for each
location being detoured.

3. The CONTRACTOR shall install standard traffic control devices in accordance with the Detour Signage plan
provided in the bid documents and the Manual on Uniform Traffic Control Devices (MUTCD.)

4. The detour signage shall be covered when the road closure is not in effect.

B. CONTRACTOR shall notify the following agencies of any traffic delays or road closures three days in advance of the
work:

Finance Committee - Agenda - 3/17/2021 - P199

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P199

ARTICLE 17 - MISCELLANEOUS

17.01 Giving Notice

A. Whenever any provision of the Contact Documents requires the giving of written notice, it will be deemed to have
been validly given if delivered in person to the individual or to a member of the firm or to an officer of the corporation
for whom it is intended, or if delivered at or sent by registered or certified mail, postage prepaid, to the last business
address known to the giver of the notice.

17.02 Computation of Times

Finance Committee - Agenda - 3/17/2021 - P198

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P198

5. Not resume work after the effective date of a notice of termination unless and until receipt of a written notice
from the OWNER to resume performance.

Finance Committee - Agenda - 3/17/2021 - P197

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P197

ARTICLE 15 - SUSPENSION OF WORK AND TERMINATION

15.01 Zermination, Abandonment, or Suspension at Will

The OWNER, in its sole discretion, shall have the right to terminate, abandon, or suspend all or part of the project and
contract at will. If the OWNER chooses to terminate, abandon, or suspend all or part of the project, it shall provide
CONTRACTOR 10 day’s written notice of its intent to do so.

Finance Committee - Agenda - 3/17/2021 - P196

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P196

required by subparagraph 5.04.B.7; (ii) consent of the surety, if any, to final payment; and (iii) complete and legally
effective releases or waivers (satisfactory to OWNER) of all Lien rights arising out of or Liens filed in connection
with the Work.

Finance Committee - Agenda - 3/17/2021 - P195

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P195

or corrected) reflecting such changes from the tentative certificate as ENGINEER believes justified after consideration
of any objections from OWNER. At the time of delivery of the tentative certificate of Substantial Completion
ENGINEER will deliver to OWNER and CONTRACTOR a written recommendation to division of responsibilities pending
final payment between OWNER and CONTRACTOR with respect to security, operation, safety, and protection of the
Work, maintenance, heat, utilities, insurance, and warranties and guarantees. Unless OWNER and CONTRACTOR agree