10.
TIE-IN AT SIDE ROAD
Side road tie-in areas shall be milled to the same depth as specified for the roadway.
INTERIM MILESTONES FOR SUBSTANTIAL MPLETI
The following Substantial Completion Milestones shall be met:
50 percent of the total length of all roadways segments in the contract shall be substantial
complete by July 16, 2021.
85 percent of the total length of all roadways segments in the contract shall be substantial
complete by September 3, 2021.
The entire length of all roadways segments shall be substantially completed by October
15, 2021.
COMPLETION OF WORK ON INDIVIDUAL STREETS
Streets specified as 1.5” or 2” mill and overlay shall have all ADA ramp work completed
and be final paved within three weeks of milling.
Streets specified as reclaim shall be binder paved within two weeks of reclamation. All
ADA ramp work shall be completed within three weeks after placement of binder
pavement.
Reclaim streets shall be final paved within two weeks after structures have been raised to
their final elevation, and ADA ramp work has been completed.
Failure to pave individual streets within the specified time frames without reasonable
cause shall be considered nonperformance.
The ENGINEER may remove streets from the scope of the Contract should repeated
instances of nonperformance occur.
The determination of whether or not delay in paving individual streets occurred with
reasonable cause will be at the ENGINEER’s discretion.
WORK HOURS
Reference is made to Section 6.02 Labor; Working Hours of the General Conditions.
Normal working hours shall be from 7:00 AM to 5:00 PM Monday through Friday. No
weekend, holiday or night work will be allowed without advance written approval of the
City ENGINEER.
Requests for work beyond those hours normally allowed on weekdays shall be made by
the CONTRACTOR at least 72 hours in advance.
Requests for work on Saturdays, Sundays and holidays shall be made at least one week in
advance.
CONTRACTOR should not assume requests for hours beyond the hours and days
normally allowed will be approved. Requests will be considered on a case by case basis.