Board Of Aldermen - Agenda - 10/6/2020 - P18
or failure to perform its obligations under this Contract, then ESCO will notify Customer in
writing of the existence, extent of, and reasons for such delay. ESCO shall have no claim for
additional compensation on account of such delays but ESCO and Customer may extend
the contract time by revision to the Scope of Work for such reasonable time as they shall
agree. If Customer determines that a delay described in the first sentence of this section will
result in ESCO not completing the Work for a period of ninety (90) days or more, then
Customer or ESCO may terminate this Contract and the Customer shall pay ESCO for the
portion of the Work completed up to the Contract termination date.
5.9 Equipment Location andAccess
The parties understand and agree that the Premises will be occupied during construction.
ESCO shall take all necessary precautions to ensure the public safety and convenience of
the occupants during construction and Customer shall cooperate with ESCO’s reasonable
requirements and related requirements described in Attachments 2 and 4. ESCO shall
complete the Work in accordance with the schedule in Attachment 2 - Maintenance and
Service Agreement. ESCO shall use sufficient personnel and adequate equipment to
complete the Work pursuant to Section 5.01.
The Work must be completed in a continuous uninterrupted operation on the days and
between the hours specified in Attachment 7 - Additional Requirements, unless otherwise
authorized in writing by the Customer. No Work is to be done on holidays, Saturdays, or
Sundays except as contemplated in Attachment 7 - Additional Requirements, the Scope of
Work in order to maintain the Standards of Comfort described in Attachment 8 - Standards
of Comfort or in the event of emergencies unless otherwise approved by Customer. The
Customer will provide access to the Premises at the times agreed upon and make all
reasonable provisions for ESCO to enter the Premises where Work is to be performed so
that Work may be performed in an efficient manner.
ESCO is responsible for the security of partially completed work and for uninstalled
materials or equipment stored at Customer properties. Only materials and equipment
intended and necessary for immediate use shall be brought into the buildings. Equipment
and unused materials shall be removed from each building by the end of each workday
unless overnight storage is provided for within the Scope of Work. The
Customer shall provide if available, without charge, a mutually satisfactory location or
locations for the storage and operation of materials and equipment and the performance of
the Work, including a location for staging and mobilization.
Flammables and combustibles shall be stored only in accordance with the requirements of
relevant statutes, regulations, NFPA standards and Customer procedures. In the eventthat
the Customer is unable to provide a satisfactory location for the storage of flammables and
combustibles, then ESCO shall provide and pay for suitable storage.
5.10 Permits and Fees
ESCO shall secure and pay for building and other permits and governmental fees, licenses,
and inspections necessary for proper performance and completion of the Work that are
required by federal, state, or town or city governments. In the event that fees for any permits
are reduced or waived by request, standing or intervention of the Customer, then, at the
Customer’s option, the amount of the savings of the fee shall be deducted from the line item
14 ESCO Contract — Nashua Schools & EEI, Inc.