Finance Committee - Agenda - 3/17/2021 - P405
21.
22.
23.
24.
25.
26.
PROTECTI FLANDSCAPI
CONTRACTOR shall take appropriate measures to protect trees, shrubs and other
landscaping. Branches, limbs and roots shall not be cut except with permission of the
ENGINEER.
Where cutting is necessary, work shall be performed by qualified workers.
RESTORATI FEXISTI PROPERTY
The CONTRACTOR shall be responsible for the preservation of all public and private
property and structures, and shall use every precaution necessary to prevent damage
thereto. If damage is done to public or private property, such property shall be promptly
restored by the CONTRACTOR, at his/her expense, to a condition similar or equal to
that existing before the damage was done, to the satisfaction of the ENGINEER.
Failure to promptly restore existing property and structures including, but not limited to
driveways and lawns, may result in the ENGINEER’s determination that associated work
is not complete and therefore not eligible for progress payment. Such associated work
may include, but not be limited to paving, pipe installation, catch basins, manholes and
curbing.
Unless specifically agreed to in advance, driveway tie-ins will be paved concurrent with
top course paving operations.
In no circumstances shall driveway tie-ins not be completed within two weeks of the
adjacent top course paving.
PERATI ITH REFUSE PICKUP
The CONTRACTOR shall determine the schedule for trash pickup by contacting the City
of Nashua’s Solid Waste Department. The CONTRACTOR shall cooperate and make
arrangements to insure that trash pickup is not delayed or obstructed in any way. This
may involve the CONTRACTOR bringing trash barrels to the front or backside of the
work area for pickup by the Solid Waste Department and then returning the barrels back
to each house.
PERATI ITH ALITY A RANCE
A minimum of one core per street shall be taken. Cores shall be cut and delivered to
the City within 24 hours of pavement placement. Core locations will be selected
randomly by the ENGINEER. Failure to cut and deliver cores may result in delay of
progress payments for pavement.
PROPERTY I RANCE
Property insurance is referenced in the General Conditions (Article 5.05).
Property insurance is not required for this contract.
ACCESS TO PRODUCTION FACILITIES
The City of Nashua may choose to have inspection and testing performed at the asphalt
plant. All relevant provisions of the Standard Specifications, including but not limited
to Section 3.1.6 Access to Production Facilities — General, shall apply.
SC - 8 of 9