SUPPLEMENTARY CONDITIONS
These Supplementary Conditions amend or supplement the Standard General Conditions of the
Construction Contract and other provisions of the Contract Documents as indicated below. All
provisions which are not so amended or supplemented remain in full force and effect.
ARTICLE 2 — PRELIMINARY MATTERS
SC-2.06B Subcontractor’s Pre-Construction Meetings
Each Individual Subcontractor will be required to attend a Pre-Construction Meeting to
discuss technical, safety, schedule and other issues. Each meeting shall be attended by
the Subcontractor’s responsible person in charge for the work and by the contractor’s
superintendent.
ARTICLE 6 -- CONTRACTOR'S RESPONSIBILITY
SC-6.01C Supervision and Superintendence
Machine operators, including operators of paving machines, will not be considered
Superintendents. The Superintendent is expected to attend regularly scheduled progress
meetings.
Night work may be necessary on streets with high daily traffic. High traffic streets are:
a. West Hollis St
b. Main Dunstable Rd.
c. Daniel Webster Highway
ARTICLE 17 -- MISCELLANEOUS
SC-17.10 Coordination with other parties:
CONTRACTOR is expected to work with the City to address minor drainage issues in
existing roadways. Resolution to drainage issue can entail shimming, milling, and/or
modifications to proposed road treatment.
SC - 1 of 1