Finance Committee - Agenda - 7/6/2016 - P85

By dnadmin on Mon, 11/07/2022 - 09:51
  • Read more about Finance Committee - Agenda - 7/6/2016 - P85

Exhibit A
Nashua - Crown Street Park & Ride Project
Scope of Work and Task Descriptions
June 15, 2016

d. Fill the casing with water to a depth of 24 inches and allow to pre-soak for 24 hours;

e. After pre-soaking, refill the casing with 24 inches of water and record the drop in
water level from the top of the casing at the end of one hour;

f. Divide the drop in water elevation by one hour to obtain the infiltration rate for the
given observation;

Finance Committee - Agenda - 7/6/2016 - P84

By dnadmin on Mon, 11/07/2022 - 09:51
  • Read more about Finance Committee - Agenda - 7/6/2016 - P84

Exhibit A
Nashua - Crown Street Park & Ride Project
Scope of Work and Task Descriptions
June 15, 2016

exploration program. The test borings will be backfilled with the drill cuttings and sand fill, if
needed.

A GZA engineer will coordinate and observe the drilling, classify soil samples, and prepare
individual logs for each exploration. The as-drilled test boring locations will be determined by GZA
using tape ties from prominent site features and/or hand-held GPS, which has a precision of +/- 10
feet.

Finance Committee - Agenda - 7/6/2016 - P83

By dnadmin on Mon, 11/07/2022 - 09:51
  • Read more about Finance Committee - Agenda - 7/6/2016 - P83

Exhibit A
Nashua - Crown Street Park & Ride Project
Scope of Work and Task Descriptions
June 15, 2016

Task 2.2 — Geotechnical Investigations

Finance Committee - Agenda - 7/6/2016 - P82

By dnadmin on Mon, 11/07/2022 - 09:51
  • Read more about Finance Committee - Agenda - 7/6/2016 - P82

Exhibit A
Nashua - Crown Street Park & Ride Project
Scope of Work and Task Descriptions
June 15, 2016

Task 2 — Preliminary Design

For the purposes of this scope of work, MJ has assumed that the preferred alternative will include
demolishing the existing warehouse building and constructing a 250 space Park & Ride lot. Ifa
different preferred alternative is selected, the scope and fee will be re-evaluated.

Task 2.1 — Preliminary Plans

Finance Committee - Agenda - 7/6/2016 - P81

By dnadmin on Mon, 11/07/2022 - 09:51
  • Read more about Finance Committee - Agenda - 7/6/2016 - P81

Exhibit A
Nashua - Crown Street Park & Ride Project
Scope of Work and Task Descriptions
June 15, 2016

Task 1.6 — Alternatives Development
With consultation with the City, up to three (3) alternatives will be developed potentially including:

250 Space Park & Ride Lot assuming the existing warehouse building will remain

Finance Committee - Agenda - 7/6/2016 - P80

By dnadmin on Mon, 11/07/2022 - 09:51
  • Read more about Finance Committee - Agenda - 7/6/2016 - P80

Exhibit A
Nashua - Crown Street Park & Ride Project
Scope of Work and Task Descriptions
June 15, 2016

Since the NEPA process has been completed for this project, it is assumed that the project will not
need to be presented at the monthly NHDOT Natural Resource or Cultural Resource meetings.

Task 1.4 — Existing Structure Review

Finance Committee - Agenda - 7/6/2016 - P79

By dnadmin on Mon, 11/07/2022 - 09:51
  • Read more about Finance Committee - Agenda - 7/6/2016 - P79

Exhibit A
Nashua - Crown Street Park & Ride Project
Scope of Work and Task Descriptions
June 15, 2016

Finance Committee - Agenda - 7/6/2016 - P78

By dnadmin on Mon, 11/07/2022 - 09:51
  • Read more about Finance Committee - Agenda - 7/6/2016 - P78

Exhibit A
Nashua - Crown Street Park & Ride Project
Scope of Work and Task Descriptions
June 15, 2016

Task 1 — Engineering Study
Task 1.1 — Information Gathering

MJ will review previous studies and collect available data for the City-owned property at 25 Crown
Street and a piece of City-owned property off Gillis Street. This will include the following:

Traffic Count Data

Phase I/II Environmental Site Assessment
Existing utility information

Crash history on roadways

Finance Committee - Agenda - 7/6/2016 - P77

By dnadmin on Mon, 11/07/2022 - 09:51
  • Read more about Finance Committee - Agenda - 7/6/2016 - P77

Exhibit A
Nashua - Crown Street Park & Ride Project
Scope of Work and Task Descriptions
June 15, 2016

The following scope of work outlines the necessary tasks to be undertaken by McFarland-Johnson
(MJ) and its sub-consultants to determine the solutions, prepare plans, obtain permits, and
ultimately advertise the Crown Street Park and Ride project for construction. The project has been
organized into three specific tasks to take the project from planning through to construction.

Finance Committee - Agenda - 7/6/2016 - P76

By dnadmin on Mon, 11/07/2022 - 09:51
  • Read more about Finance Committee - Agenda - 7/6/2016 - P76

McFARLAND JOHNSGN TEAM
NE Pas

CRUWN STREET PARK & RIVE PROJECT
NASHUA, NEW HAMPSHIRE
June 15, 2016

McFARLAND JOHNSON $48,362.01 $36,040.70 $34,446.64 $118,849.35 $3,950.00 $122,799.35
GM2 ASSOCIATES, INC. $33,564.88 $33,564.88 $40.00 $33,604.88
GZA GEOENVIRONMENTAL, INC. : $22,383.30 : $22,383.30 $14,487.20 $36,870.50
DESIGN WORKS $2,000.00 $2,000.00 $1,000.00 $5,000.00 $0.00 $5,000.00

TOTAL $83,926.89 $60,424.00 $35,446.64 $179,797.53 $18,477.20 $198,274.73

PROJECT TOTAL $108,274.73