SECTION 01780

PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.1 MAINTENANCE OF PROJECT RECORD DOCUMENTS AND SAMPLES

A.

B.

CONTRACTOR shall document the construction using red-lined drawings.

CONTRACTOR shall maintain at the site for OWNER’s permanent record one
complete set of project documents that includes a copy of the: Drawings, red-
lined drawings, Specifications, Addenda, Change Orders, Submittals and Shop
Drawings, quality control field reports, product data, equipment manuals, and
material samples.

Finance Committee - Agenda - 3/17/2021 - P523

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P523

Section 01520 - Construction Facilities and Temporary Controls Page 2 of 2
January 2021 3066.21

1.4 REMOVAL OF UTILITIES, FACILITIES AND CONTROLS
A. CONTRACTOR shall remove temporary facilities, equipment, and materials that
CONTRACTOR installed during the performance of the Contract Work.
CONTRACTOR shall restore existing and permanent facilities used during the
performance of Work to original or better condition.
PART 2 - PRODUCTS
Not used.

PART 3 - EXECUTION

Not used.

[END OF SECTION 01520]

Finance Committee - Agenda - 3/17/2021 - P522

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P522

SECTION 01520

CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

PART 1 - GENERAL

1.1

1.2

1.3

SUMMARY

A.

CONTRACTOR shall maintain areas outside the limits of work free of waste
materials, debris, and rubbish that are a direct result of work performed by
CONTRACTOR.

TEMPORARY UTILITIES

A.

CONTRACTOR shall provide drinking water for his employees, ENGINEER, and
OWNER’s representatives.

CONTRACTOR shall provide portable sanitary facilities for use by all project
personnel.

Finance Committee - Agenda - 3/17/2021 - P521

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P521

Section 01450 - Quality Control Page 2 of 2

January 2021

3066.21

made, if desired, for observation before shipment from the place of
manufacture. CONTRACTOR must anticipate that possible delays may occur
due to the necessity of materials being inspected and accepted for use.

1.3 SUBSTANDARD WORK OR MATERIALS

A.

Finance Committee - Agenda - 3/17/2021 - P520

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P520

SECTION 01450

QUALITY CONTROL

PART 1 - GENERAL

1.1 GENERAL QUALITY CONTROL

A.

CONTRACTOR - shall maintain quality control over the _ suppliers,
manufacturers, products, services, site conditions, and workmanship to
produce Work of specified quality.

CONTRACTOR shall comply with industry standards except when more
restrictive tolerances or specified requirements indicate more rigid standards
or more precise workmanship.

Finance Committee - Agenda - 3/17/2021 - P519

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P519

Section 01330 - Submittals Page 4 of 4
January 2021 3066.21

7. Applicable standards, such as ASTM or Federal Specification numbers;
8. Identification of deviations from Contract Documents; and
9. Identification of revisions on resubmittals.

19 RESUBMISSION REQUIREMENTS

A. CONTRACTOR shall make any and all corrections or changes in submittals
required by ENGINEER, and resubmit revised versions. Submittals shall not be
accepted until ENGINEER reviews and approves of revised versions.

Finance Committee - Agenda - 3/17/2021 - P518

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P518

Section 01330 - Submittals Page 3 of 4
January 2021 3066.21
B. CONTRACTOR shall complete all of the following items no later than the

specified number of calendar days.

Associated shipping, work, and use of

materials by CONTRACTOR shall not begin until ENGINEER’s review of each
respective submittal is complete and where resubmission by CONTRACTOR is
not required by ENGINEER. ENGINEER shall reply to CONTRACTOR within 7
calendar days of receipt of each submittal and state whether or not

CONTRACTOR must resubmit.

Submittal

Finance Committee - Agenda - 3/17/2021 - P517

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P517

Section 01330 - Submittals Page 2 of 4
January 2021 3066.21

1.4

1.5

1.6

1.7

1.8

C. The schedule shall account for ENGINEER’s Contract Administration and
quality control responsibilities.

PRODUCT DATA

A. CONTRACTOR shall submit copies of product data sheets as required in the
Specifications. CONTRACTOR shall clearly mark each copy of product data
sheets to identify applicable products, models, options, and other data.

MANUFACTURER'S INSTRUCTIONS

Finance Committee - Agenda - 3/17/2021 - P516

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P516

SECTION 01330

SUBMITTALS

PART 1 - GENERAL

1.1

1.2

1.3

DESCRIPTION

A.

This section specifies the general requirements and procedures for preparing
and transmitting data to ENGINEER for their information or review.
CONTRACTOR shall deliver all submittals to ENGINEER in a form acceptable to
ENGINEER.

CONTRACTOR'S DRAWINGS

A.

D.

The Drawings shall show the general arrangement and details as necessary to
provide a comprehensive description of the work to be performed.

Finance Committee - Agenda - 3/17/2021 - P515

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P515

Section 01320- Survey Control Page 2 of 2

January 2021

3066.21

PART 3 - EXECUTION

3.1

GENERAL

A.

CONTRACTOR shall obtain as-built elevation information using the site
coordinate system and datum (in the New Hampshire State Plane coordinate
system, vertical datum NAVD-88, as indicated on the Drawings).

The survey equipment used shall have a precision to the 0.01 feet.

As-built information shall include horizontal and vertical coordinate

information for the following: