Finance Committee - Minutes - 12/15/2021 - P1

By dnadmin on Mon, 11/07/2022 - 13:50
  • Read more about Finance Committee - Minutes - 12/15/2021 - P1

REPORT OF THE FINANCE COMMITTEE
DECEMBER 15, 2021

A meeting of the Finance Committee was held on Wednesday, December 15, 2021, at 7:00 p.m. in the
Aldermanic Chamber and via Zoom. The meeting link information can be found on the agenda.

Mayor Jim Donchess, Chairman, presided.

Members of the Committee present: Mayor Jim Donchess
Alderman Patricia Klee, Vice Chair
Alderman-at-Large Michael B. O’Brien, Sr.
Alderman-at-Large Brandon Michael Laws (via Zoom)
Alderman Linda Harriott-Gathright

Finance Committee - Agenda - 11/17/2021 - P195

By dnadmin on Mon, 11/07/2022 - 13:50
  • Read more about Finance Committee - Agenda - 11/17/2021 - P195

GPI Engineering | Design | Planning | Construction Management

October 29, 2021

Camille Correa

Nashua Transit System
11 Riverside Street
Nashua, NH 03060

SUBJECT: NTC Time Extension Recommendation
Dear Camille:

GPI has reviewed the time extension request from D.L. King & Associates, Inc. submitted and dated October 24,
2021. After review, there are some comments and recommendations GPI has on the merits of the request as are
described below:

Recommendation for Substantial Completion date

Finance Committee - Agenda - 11/17/2021 - P194

By dnadmin on Mon, 11/07/2022 - 13:50
  • Read more about Finance Committee - Agenda - 11/17/2021 - P194

Changer Order 01 Items List - To Be Field Measured for Payment
ORIGINAL BID PRICE ITEM TOTAL
Item Number |Quantity |Unit Description
203.1 28|CY COMMON EXCAVATION $ 23.40 | $ 655.20
304.2 43]CY GRAVEL $ 35.10 | $ 456.30
304.3 10|CyY CRUSHED GRAVEL $ 40.95 | $ 409.50
403.12 7|TON [HOT BITUMINOUS PAVEMENT, HAND METHOD $ 200.00 | $ 1,400.00
608.26 28|SY 6" CONCRETE SIDEWALK $ 48.80 | $ 1,366.40
628.1 31)LF SAWED CONCRETE PAVEMENT $ 21.06 | $ 652.86
628.2 41) LF SAWED BITUMINOUS PAVEMENT $ 16.38 | $ 671.58

Finance Committee - Agenda - 11/17/2021 - P193

By dnadmin on Mon, 11/07/2022 - 13:50
  • Read more about Finance Committee - Agenda - 11/17/2021 - P193

K
ELM STREET o
PARKING GARAGE a
Or et Aaa taieble uv
Vaasa eet pros mi away GP
PAVEMENT TRA
Cane YE t
sree rl ene mrwcion |
nanan craeer Se
aaa Eoenete
oa eu ed Rom pede

PHO®. LANDSCAPE
‘AREA

aetna F ne
nat
Nos
wna
oo = mE
a —— 1g UGARDEM
paoreaiiarne sm m| eves
niacin f eueas

a

PROP, MLL A LAY
eeteetnt Hhspiatthond S|
jer math

aera ayers,
‘Seat cia pa

Moet re Sia
ay 2

MOF, CEYTATT ep
(COLGRETE SPEAK

Finance Committee - Agenda - 11/17/2021 - P192

By dnadmin on Mon, 11/07/2022 - 13:50
  • Read more about Finance Committee - Agenda - 11/17/2021 - P192

CHANGE ORDER

No. 1

PROJECT: Nashua Transit Center Retrofit

OWNER'S CONTRACT NO.: __ REPO979-040821

EXECUTED CONTRACT DATE: July 15, 2021

DATE OF ISSUANCE: _ September 9, 2021. EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH

OWNER’s Purchase Order NO.: 165194

CONTRACTOR: DL King & Associates, Inc.

ENGINEER: Greenman-Pedersen, Inc.

The Contract is modified as follows upon execution of this Change Order:

Finance Committee - Agenda - 11/17/2021 - P191

By dnadmin on Mon, 11/07/2022 - 13:50
  • Read more about Finance Committee - Agenda - 11/17/2021 - P191

CHANGE ORDER
SUMMARY

CHANGE IN CONTRACT PRICE

Original Contract Price:

$1,129,710.00

CHANGE IN CONTRACT TIMES

Original Contract Times:

Substantial Completion: October 17, 2021

Ready for Final Payment: November 16, 2021

Net Changes from previously approved Change Orders

$0

Net Changes from previously approved Change Orders
Substantial Completion: 0

Ready for Final Payment: O

Contract Price prior to this Change Order:

§ 1,129,720.00

Finance Committee - Agenda - 11/17/2021 - P190

By dnadmin on Mon, 11/07/2022 - 13:50
  • Read more about Finance Committee - Agenda - 11/17/2021 - P190

CHANGE ORDER
SUMMARY

CHANGE IN CONTRACT PRICE

Original Contract Price:

$ 1,129,710.00

CHANGE IN CONTRACT TIMES
Original Contract Times:

Substantial Completion: October 17, 2021

Ready for Final Payment: November 16, 2021

Net Changes from previously approved Change Orders

§ 5,611.84

Net Changes from previously approved Change Orders
Substantial Completion: 7

Ready for Final Payment: 7

Contract Price prior to this Change Order:

$ 1,135,321.84

Finance Committee - Agenda - 11/17/2021 - P189

By dnadmin on Mon, 11/07/2022 - 13:50
  • Read more about Finance Committee - Agenda - 11/17/2021 - P189

Attachments:
e DL. King COR# 2 Proposal CB-130 Extra Work

« O.L. King COR# 3 Proposal DMH-520 Adjustment
e =6D.L. King COR# 10 Proposal Porcelain/Epoxy Grout

Change Order #2 2 of 3

Finance Committee - Agenda - 11/17/2021 - P188

By dnadmin on Mon, 11/07/2022 - 13:50
  • Read more about Finance Committee - Agenda - 11/17/2021 - P188

CHANGE ORDER

No. 2

PROJECT: Nashua Transit Center Retrofit
OWNER'S CONTRACT NO.: —RFPO979-040821
EXECUTED CONTRACT DATE: July 15, 2021

DATE OF ISSUANCE: _ November 1, 2021 — EFFECTIVE DATE: Upon City Approval

OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 165194
CONTRACTOR: DL King & Associates, Inc.

ENGINEER: Greenman-Pedersen, Inc.

The Contract is modified as follows upon execution of this Change Order:

Description:

Finance Committee - Agenda - 11/17/2021 - P187

By dnadmin on Mon, 11/07/2022 - 13:50
  • Read more about Finance Committee - Agenda - 11/17/2021 - P187

Date: November 3, 2021
To: John Griffin, CFO; Kelly Parkinson, Purchasing Manager
From: Camille Correa, Transit Administrator

Re: _ Transit Center Retrofit project change orders

The City of Nashua was awarded grants from the Federal Transit Administration for the Nashua
Transit System to retrofit the Transit Center and surrounding sidewalks and roadway.