17.07 Road Closures and Traffic Delays
A. Partial or full closure of streets in order to facilitate construction will be permitted, or required by the Engineer in
accordance with the following:
1. If the CONTRACTOR proposes a closure, the CONTRACTOR notifies the OWNER in writing at least 5 days
prior to the proposed closure of his intent to close the road.
2. At least 5 days prior to the proposed closure, the CONTRACTOR shall submit a detour traffic plan for each
location being detoured.
Finance Committee - Agenda - 6/3/2020 - P255
until the submitting party has delivered the written statement of its position and full documentation to the other party.
The parties shall then attempt to resolve the dispute through good faith efforts and negotiation between the OWNER
Representative and a CONTRACTOR Representative. At all times, CONTRACTOR shall carry on the work under
this contract and maintain and complete work in accordance with the requirements of the contract or determination or
Finance Committee - Agenda - 6/3/2020 - P254
professional manner. CONTRACTOR shall be given an opportunity for consultation with the OWNER prior to the
effective date of the termination. CONTRACTOR may terminate the contract on 10 calendar days written notice if,
through no fault of CONTRACTOR, the OWNER fails to pay CONTRACTOR for 45 days after the date of approval
by the OWNER of any Application for Payment.
Upon receipt of notice of termination for cause, CONTRACTOR shall:
i. Immediately discontinue work on the date and to the extent specified in the notice.
Finance Committee - Agenda - 6/3/2020 - P253
14.08 Final Completion Delayed
Finance Committee - Agenda - 6/3/2020 - P252
2. No occupancy or separate operation of part of the Work may occur prior to compliance with the requirements of
paragraph 5.10 regarding property insurance.
14.06 Final Inspection
Finance Committee - Agenda - 6/3/2020 - P251
3. If it is subsequently determined that OWNER's refusal of payment was not justified, the amount wrongfully
withheld shall be treated as an amount due as determined by paragraph 14.02.C.1.
14.03 CONTRACTOR’S Warranty of Title
A. CONTRACTOR warrants and guarantees that title to all Work, materials, and equipment covered by any
Application for Payment, whether incorporated in the Project or not, will pass to OWNER no later than the time of
payment free and clear of all Liens.
14.04 Substantial Completion
Finance Committee - Agenda - 6/3/2020 - P250
c. OWNER has been required to correct defective Work or complete Work in accordance with paragraph
13.09; or
d. ENGINEER has actual knowledge of the occurrence of any of the events enumerated in paragraph 15.02.A.
B. Applications for Payments.
1.
Finance Committee - Agenda - 6/3/2020 - P249
14.02 Progress Payment
A. Review of Applications.
1. Prior to submittal of Application for Payment to OWNER (but not more often than once a month), the
CONTRACTOR shall submit the monthly progress estimate to the ENGINEER for review and approval.
Finance Committee - Agenda - 6/3/2020 - P248
13.08 Acceptance of Defective Work