Finance Committee - Agenda - 6/3/2020 - P277

By dnadmin on Mon, 11/07/2022 - 13:30
  • Read more about Finance Committee - Agenda - 6/3/2020 - P277

The following Construction Specifications amend, revise, supplement and/or otherwise modify
the New Hampshire Department of Transportation’s STANDARD SPECIFICATIONS FOR
ROADWAY AND BRIDGE CONSTRUCTION (2016 edition as amended).

Finance Committee - Agenda - 6/3/2020 - P276

By dnadmin on Mon, 11/07/2022 - 13:30
  • Read more about Finance Committee - Agenda - 6/3/2020 - P276

NHDOT SUPPLEMENTAL SPECIFICATIONS
(2016 EDITION) — UPDATED JULY 6, 2018

Finance Committee - Agenda - 6/3/2020 - P275

By dnadmin on Mon, 11/07/2022 - 13:30
  • Read more about Finance Committee - Agenda - 6/3/2020 - P275

DIVISION 9

TECHNICAL SPECIFICATIONS

A. NHDOT Supplemental Specifications (2016 Edition) — updated July 6, 2018
B. Special Provisions

Finance Committee - Agenda - 6/3/2020 - P274

By dnadmin on Mon, 11/07/2022 - 13:30
  • Read more about Finance Committee - Agenda - 6/3/2020 - P274

CONTRACTOR'S FINAL RELEASE AND WAIVER OF LIEN

Project:
Owner Contractor
Owner: _City of Nashua, New Hampshire Name:
Address:_229 Main Street Address:
Nashua, New Hampshire 03060
City State Zip City State Zip

Contractor License:

Contract Date:

TO ALL WHOM IT MAY CONCERN:

Finance Committee - Agenda - 6/3/2020 - P273

By dnadmin on Mon, 11/07/2022 - 13:30
  • Read more about Finance Committee - Agenda - 6/3/2020 - P273

CONTRACTOR'S AFFIDAVIT

STATE OF:

COUNTY OF:

Before me, the undersigned, a

(Notary Public, Justice of Peace, Alderman)
in and for said County and State personally appeared,

(Individual, Pariner or duty authorized representative of corporate contractor)
who being duly sworn according to law deposes and says that the cost of all the Work, and
outstanding claims and indebtedness of whatever nature arising out of the performance of the
contract between

Finance Committee - Agenda - 6/3/2020 - P272

By dnadmin on Mon, 11/07/2022 - 13:30
  • Read more about Finance Committee - Agenda - 6/3/2020 - P272

CONSENT OF SURETY FOR FINAL PAYMENT

OWNER’S CONTRACT NO. :

PROJECT:

TYPE OF CONTRACT:

AMOUNT OF CONTRACT (INCLUDING CHANGE ORDERS):

CONTRACTOR:

CONTRACT FOR:

CONTRACT DATE:

In accordance with the provisions of the above named contract between the OWNER and the CONTRACTOR,
the following named Surety Company:

On the Payment Bond of the following named CONTRACTOR:

Finance Committee - Agenda - 6/3/2020 - P271

By dnadmin on Mon, 11/07/2022 - 13:30
  • Read more about Finance Committee - Agenda - 6/3/2020 - P271

CERTIFICATE OF FINAL COMPLETION

PROJECT:

OWNER’S CONTRACT NO:

DATE OF ISSUANCE:

OWNER:

OWNER’s Purchase Order NO.:

CONTRACTOR:

City of Nashua, NH

ENGINEER:

The Work to which this Certificate applies has been inspected by authorized representative of OWNER,
CONTRACTOR, and ENGINEER, and that Work is hereby declared to be substantially complete in
accordance with the Contract Documents on

(DATE OF FINAL COMPLETION)

Finance Committee - Agenda - 6/3/2020 - P270

By dnadmin on Mon, 11/07/2022 - 13:30
  • Read more about Finance Committee - Agenda - 6/3/2020 - P270

CERTIFICATE OF SUBSTANTIAL COMPLETION

PROJECT:

OWNER’S CONTRACT NO:

DATE OF ISSUANCE:
OWNER: City of Nashua, NH

OWNER’s Purchase Order NO.:

CONTRACTOR:

ENGINEER:

The Work to which this Certificate applies has been inspected by authorized representative of OWNER,
CONTRACTOR, and ENGINEER, and that Work is hereby declared to be substantially complete in
accordance with the Contract Documents on

(DATE OF SUBSTANTIAL COMPLETION)

Finance Committee - Agenda - 6/3/2020 - P269

By dnadmin on Mon, 11/07/2022 - 13:30
  • Read more about Finance Committee - Agenda - 6/3/2020 - P269

Summary

CHANGE IN CONTRACT PRICE:

Original Contract Price

5

Final completion:

CHANGE IN CONTRACT TIMES:
Original Contract Times

Ready for final payment:

Net changes from previous Change Orders

$

Net change from previous Change Orders

Contract Price prior to this Change Order

3

Final completion:

Contract Times prior to this Change Order

Ready for final payment:

Net Increase (decrease) of this Change Order

$

Net Increase (decrease) of this Change Order

Finance Committee - Agenda - 6/3/2020 - P268

By dnadmin on Mon, 11/07/2022 - 13:30
  • Read more about Finance Committee - Agenda - 6/3/2020 - P268

CHANGE ORDER

No.
PROJECT:
OWNER’S CONTRACT NO:
EXECUTED CONTRACT DATE:
DATE OF ISSUANCE: EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH

OWNER’s Purchase Order NO.:

CONTRACTOR:

ENGINEER;

You are directed to make the following changes in the Contract Documents:

Description:

Pagination