Board Of Aldermen - Minutes - 12/16/2019 - P73

By dnadmin on Sun, 11/06/2022 - 22:31
  • Read more about Board Of Aldermen - Minutes - 12/16/2019 - P73

Q
A.

Q
A.

Will lessons learned from the high school construction be utilized?

Yes, several parties in the current design process were part of the construction of the high
school projects and intend to utilize the best practices and lessons learned during the
design and construction of these projects. The design team will also be engaging
periodically with school district staff, principals and teachers in this regard as well.

Board Of Aldermen - Minutes - 12/16/2019 - P72

By dnadmin on Sun, 11/06/2022 - 22:31
  • Read more about Board Of Aldermen - Minutes - 12/16/2019 - P72

> p

> p

> p

> p

> p

> p

Building Construction Plaques: The Elm Street plaque is located in the Keefe Auditorium
and for now will remain there. At Fairgrounds and Pennichuck they will only be relocated
if necessary due to construction. New updated plaques will be located in the same areas.

Is there a budget for packing and moving?
Yes, moving costs are included in the budget.

Will there be new furniture? How will the furniture specifically ensure for long term
durability?

Board Of Aldermen - Minutes - 12/16/2019 - P71

By dnadmin on Sun, 11/06/2022 - 22:31
  • Read more about Board Of Aldermen - Minutes - 12/16/2019 - P71

NASHUA MIDDLE SCHOOLS PROJECT

FREQUENTLY ASKED QUESTIONS

GENERAL

Q
A.

> p

> p

> p

>p

Why was this middle school improvement program initiated?

Board Of Aldermen - Minutes - 12/16/2019 - P70

By dnadmin on Sun, 11/06/2022 - 22:31
  • Read more about Board Of Aldermen - Minutes - 12/16/2019 - P70

Committee Recommendation

Build new facility at Landfill

- We care about a safe and healthy work environment for our staff
- Attention to infrastructure long overdue

- Cost is 38% less to build new ($9.9M) vs. to renovation ($15.9M)
- Noland acquisition cost or removal of land from tax rolls

- Ability for future growth

/
vs
©
a
ma
=
i)
3)
7)
ioe
Oo}
cS
oy
in
©
12

- Energy and workplace efficiencies

EWEN Ins) even

Board Of Aldermen - Minutes - 12/16/2019 - P69

By dnadmin on Sun, 11/06/2022 - 22:31
  • Read more about Board Of Aldermen - Minutes - 12/16/2019 - P69

Advantages
DPW Facilities

Benefits to Nashua

- Healthier City employees

- Better DPW service to Nashua taxpayers

- Avoid cost of future land acquisition/investment

- Reduced deferred maintenance expenses

- Generated utility costs savings

- Further commitment to sustainable City owned buildings
- Implement master plan for Landfill

- Opportunity for the Police Department to expand into the current
DPW Administration and Engineering building

- Opportunity for Conway Arena to expand with a second sheet of ice

Board Of Aldermen - Minutes - 12/16/2019 - P68

By dnadmin on Sun, 11/06/2022 - 22:31
  • Read more about Board Of Aldermen - Minutes - 12/16/2019 - P68

Advantages
DPW Facilities

New Building

- Optimum program

- Healthy environment

- Lower utility costs, less maintenance

- Shared common areas (conference rooms, meeting rooms, bathrooms,
breakrooms)

- Energy efficiencies and sustainability (building shell, photovoltaic array,
green roof, water collection, electric car spaces)

- Savings in construction general conditions

- Optimum construction timeline — less operational disruption

Operations

- Unified personnel, equipment, resources

Board Of Aldermen - Minutes - 12/16/2019 - P67

By dnadmin on Sun, 11/06/2022 - 22:31
  • Read more about Board Of Aldermen - Minutes - 12/16/2019 - P67

CITY OF NASHUA

NEW HAMPSHIRE
CITY ENGINEER'S OFFICE
9 RIVERSIDE STREET
NASHUA, NEW HAMPSHIRE 03062

REVISIONS

NO. DESCRIPTION DATE

"PROPOSED SIDEWALK

PLAN PREPARED FOR

FOUR HILLS
LANDFILL

A_REVI.OG (2

orice PROPO
“_|
I {

ADDRESS:
844 WEST HOLLIS ST

| | GREEN AREA —

WITH TABLES NASHUA, NEW HAMPSHIRE

TAX/MAP

SHEET TITLE

CONCEPT PLAN

DATE: PROJECT NUMBER

MARCH 2019

PROPOSED PAVED AREA «
APPROXIMATLY 367 PARKING.

Board Of Aldermen - Minutes - 12/16/2019 - P66

By dnadmin on Sun, 11/06/2022 - 22:31
  • Read more about Board Of Aldermen - Minutes - 12/16/2019 - P66

New Facility
DPW Facilities

Comments:
- New DPW Center
- 2-story, 25,000 SF building

- 12-month construction duration

Hard Construction Costs $7,500,000
Design Contingency (10%) $750,000
Architectural, Engineering, Planning (12%) $990,000
Geotechnical Engineering $5,000
Haz-Mat Survey $0
Furniture, Fixtures and Equipment $200,000
Owner's Contingency (5%) $472,250
Total $9,917,250

Board Of Aldermen - Minutes - 12/16/2019 - P65

By dnadmin on Sun, 11/06/2022 - 22:31
  • Read more about Board Of Aldermen - Minutes - 12/16/2019 - P65

Summary
DPW Facilities

Questions and Answers

Board Of Aldermen - Minutes - 12/16/2019 - P64

By dnadmin on Sun, 11/06/2022 - 22:31
  • Read more about Board Of Aldermen - Minutes - 12/16/2019 - P64

Comments
DPW Facilities

Ta

- x
|
a
me.)

Financial challenges with $15.9M+ of renovations

Programming of existing renovated space remains
incomplete

Insufficient parking at Administration/Engineering
Department and Street Departments

No capacity for DPW administration and operations growth

No capacity for Street Department needs (vehicle storage,
maintenance bays, truck wash)