ITEM 403.12 -HOT BITUMINOUS PAVEMENT, HAND METHOD
A. SCOPE

This work shall include paving using the hand method for driveways, curb patches, areas
between railroad crossings, areas where it is impractical to pave using machine method, as
shown on the plans, or as ordered by the Engineer. Hand method paving shall not be used where
machine method paving is required.

B. MATERIALS AND CONSTRUCTION

Finance Committee - Agenda - 3/17/2021 - P233

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P233

This required minimum asphalt content is based on the use of aggregate with a specific gravity of
2.65 to 2.70. The minimum asphalt content requirement may be adjusted when aggregate with a
higher specific gravity is used, or the minimum may be adjusted at the Engineer’s discretion if it
is believed to be in the best interest of the Department.

Hot Bituminous Pavement to be placed under NHDOT Section 401 “Method Requirements” (not
“QC/QA”).

Finance Committee - Agenda - 3/17/2021 - P232

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P232

ITEM 403.11 - HOT BITUMINOUS PAVEMENT (METHOD
SPECIFICATION), MACHINE METHOD

A. SCOPE

This work shall consist of furnishing and placing bituminous pavement to the depth shown on
the plans or ordered by the Engineer. Work shall also include obtaining asphalt samples and
asphalt cores on behalf of the City for quality control testing.

B. MATERIALS AND CONSTRUCTION

Finance Committee - Agenda - 3/17/2021 - P231

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P231

C. MEASUREMENT AND PAYMENT

This item shall be measured by the Square Yard of Reclaimed Stabilized Base Processed in
Place, 12” Deep. Payment for this item shall be at the contract unit price per Square Yard. This
payment shall also include all materials, labor, equipment, and all else needed to complete the
work under this item.

Contractor shall record the square yard of reclaimed area for each street. Payment is contingent
upon submittal of quantities in a per street format.

Page 5 of 42

Finance Committee - Agenda - 3/17/2021 - P230

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P230

ITEM 306.112 - RECLAIMED STABILIZED BASE PROCESSED IN
PLACE, 12” DEEP

A. SCOPE

Finance Committee - Agenda - 3/17/2021 - P229

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P229

ITEM 304.32 -CRUSHED GRAVEL FOR SHOULDER LEVELING
A. SCOPE

This work shall consist of furnishing and placing crushed aggregate to raise the edge of the
roadway shoulders as shown on plans or directed by the Engineer.

B. MATERIALS AND CONSTRUCTION

Finance Committee - Agenda - 3/17/2021 - P228

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P228

ITEM 203.113 - DRIVEWAY EXCAVATION AND REGRADE
A. SCOPE

This work includes removing asphalt and concrete driveway materials to subbase, regrading, and
placing new pavement in kind. This item will only be used on roadways which are being
reclaimed or as directed by the Engineer.

B. MATERIALS AND CONSTRUCTION

Finance Committee - Agenda - 3/17/2021 - P227

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P227

ITEM 203.112 - ROAD EXCAVATION AND REGRADE
A. SCOPE

This work includes repairing the subgrade including regrading and replacing removed subgrade
material with binder pavement at specific locations as directed by the Engineer.

This item will only be used at locations identified by the Engineer. In other areas where
subgrade is exposed during milling, any grading and compaction of the disturbed subgrade will
be incidental to subsequent paving.

B. MATERIALS AND CONSTRUCTION

Finance Committee - Agenda - 3/17/2021 - P226

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P226

DIVISION 9

TECHNICAL SPECIFICATIONS

Finance Committee - Agenda - 3/17/2021 - P225

By dnadmin on Mon, 11/07/2022 - 13:45
  • Read more about Finance Committee - Agenda - 3/17/2021 - P225

CONTRACTOR'S FINAL RELEASE AND WAIVER OF LIEN

Project: IFB0660-021121 2021 Paving Program - Residential Roadways

Owner Contractor
Owner:_City of Nashua, New Hampshire Name:__ Sunshine Paving, Inc
Address:_229 Main Street Address: 29 Constitution Drive
Nashua, | New Hampshire 03060 Hudson, New Hampshire 03060
City State Zip City State Zip
Contract Date:

TO ALL WHOM IT MAY CONCERN:

Pagination

  • Previous page ‹‹
  • Page 168
  • Next page ››
Subscribe to Agenda

Footer menu

  • Contact