Finance Committee - Agenda - 6/7/2017 - P397

By dnadmin on Mon, 11/07/2022 - 10:23
  • Read more about Finance Committee - Agenda - 6/7/2017 - P397

B. CONTRACTOR shall be responsible for any deductible or self-insured retention. The nsk of loss within the
identified deductible amount will be borne by CONTRACTOR, Subcontractors, or others suffering any such loss, and
if any of them wishes property insurance coverage within the limits of such amounts, each may purchase and maintain
it at the purchaser’s own expense. OWNER shall not be responsible for purchasing and maintaining any property
insurance specified in this paragraph 5.06 to protect the interests of CONTRACTOR, Subcontractors, or others in the

Finance Committee - Agenda - 6/7/2017 - P396

By dnadmin on Mon, 11/07/2022 - 10:23
  • Read more about Finance Committee - Agenda - 6/7/2017 - P396

coverage. The City may, at any time, order the contractor to stop work, suspend the contract or terminate the
contract for non-compliance. All subcontractors are subject to the same insurance requirements as the contractor.

3. Include completed operations insurance;

4. Include contractual liability insurance covering CONTRACTOR’s indemnity obligations under paragraphs 6.07,
6.11, and 6.20;

Finance Committee - Agenda - 6/7/2017 - P395

By dnadmin on Mon, 11/07/2022 - 10:23
  • Read more about Finance Committee - Agenda - 6/7/2017 - P395

the Project is located to issue Bonds or insurance policies for the limits and coverage’s so required. Such surety and
insurance companies shall also meet such additional requirements and qualifications as may be provided in the
Supplementary Conditions.

Finance Committee - Agenda - 6/7/2017 - P394

By dnadmin on Mon, 11/07/2022 - 10:23
  • Read more about Finance Committee - Agenda - 6/7/2017 - P394

E. CONTRACTOR shall not be required to resume Work in connection with such condition or in any affected area
until after OWNER has obtained any required permits related thereto and delivered to CONTRACTOR written notice:
(i) specifying that such condition and any affected area is or has been rendered safe for the resumption of Work; or (11)
specifying any special conditions under which such Work may be resumed safely. If OWNER and CONTRACTOR
cannot agree as to entitlement to or on the amount or extent, if any, of any adjustment in Contract Price or Contract

Finance Committee - Agenda - 6/7/2017 - P393

By dnadmin on Mon, 11/07/2022 - 10:23
  • Read more about Finance Committee - Agenda - 6/7/2017 - P393

4, At points where the CONTRACTOR’s operations are adjacent to public and private utilities, CONTRACTOR
shall not commence work until CONTRACTOR has made all arrangements necessary for the protection of
utilities.

Finance Committee - Agenda - 6/7/2017 - P392

By dnadmin on Mon, 11/07/2022 - 10:23
  • Read more about Finance Committee - Agenda - 6/7/2017 - P392

ENGINEER by the OWNER’s of such Underground Facilities, including OWNER, or by others. Unless it is otherwise
expressly provided in the Supplementary Conditions:

1. OWNER and ENGINEER shall not be responsible for the accuracy or completeness of any such information or
data; and

2. The cost of all of the following will be included in the Contract Price, and CONTRACTOR shall have full
responsibility for:

a. Reviewing and checking all such information and data,
b. Locating all Underground Facilities shown or indicated in the Contract Documents.

Finance Committee - Agenda - 6/7/2017 - P391

By dnadmin on Mon, 11/07/2022 - 10:23
  • Read more about Finance Committee - Agenda - 6/7/2017 - P391

1. Is of such a nature as to establish that any “technical data” on which CONTRACTOR is entitled to rely as
provided in paragraph 4.02 is materially inaccurate; or

2. Is of such a nature as to require a change in the Contract Documents; or
3. Differs materially from that shown or indicated in the Contract Documents; or

Finance Committee - Agenda - 6/7/2017 - P390

By dnadmin on Mon, 11/07/2022 - 10:23
  • Read more about Finance Committee - Agenda - 6/7/2017 - P390

F. CONTRACTOR shall be responsible for the damage or destruction of property of any character resulting from
neglect, misconduct, or omission in its manner or method of execution or the non-execution of the work, or caused by
defective work or the use of unsatisfactory materials, and such responsibility shall not be released until the work shall
have been completed and accepted and the requirements of the Construction Specifications complied with.

Finance Committee - Agenda - 6/7/2017 - P389

By dnadmin on Mon, 11/07/2022 - 10:23
  • Read more about Finance Committee - Agenda - 6/7/2017 - P389

3.04 Amending and Supplementing Contract Documents

Finance Committee - Agenda - 6/7/2017 - P388

By dnadmin on Mon, 11/07/2022 - 10:23
  • Read more about Finance Committee - Agenda - 6/7/2017 - P388

C. Clarifications and interpretations of the Contract Documents shall be issued by ENGINEER as provided in Article
9.

3.02 Reference Standards
A. Standards, Specifications, Codes, Laws, and Regulations