Board Of Aldermen - Agenda - 9/14/2021 - P137
E.
the DEPARTMENT and CITY agree to review Project to determine whether to reduce the
scope of the project or to seek additional funding sources. If the Department has additional
funds available for allocation to the project, the CITY will be responsible to provide funding
as follows:
Total Project Portion to be shared Funding Split for costs above current
Cost with City Total Project Cost
Up to $0 NVA
$3,66 1,000.00
Above Up to 80% Federal / 20% City
$3,661 ,000.00 $915,250.00
up to
$4,576,250.00