Board Of Aldermen - Minutes - 10/2/2018 - P28
Mohawk Tannery
Presentation Overview
¢ Recent Past Activities
¢ Maps & Figures
¢ Contaminants of Concern
¢ EPA’s Recommended Alternative
Mohawk Tannery
Presentation Overview
¢ Recent Past Activities
¢ Maps & Figures
¢ Contaminants of Concern
¢ EPA’s Recommended Alternative
Mohawk Tannery
Meeting with Board of Alderman
Mohawk Tannery Site
Nashua, New Hampshire
EPA Work Area
Toll Free 888-372-7341 —
=
SEPA
New England
Cranes
October 2, 2018
City Hall Auditorium, Nashua NH
Melissa Taylor, NH & RI Superfund Section Chief
Gerardo Millan-—Ramos, Remedial Project Manager
Special Bd. of Aldermen — 10/26/15 Page 26
Alderwoman Melizzi-Golja
Yes thank you and | guess that’s my concern. If 5 people have the same question, you only need to hear it
once. But people also need to know there is a process to exchange information.
President McCarthy
Work it through Sue and we will get answers.
Ms. Dumville That is what we do so we are happy to answer any of your questions.
Alderman Lopez
Special Bd. of Aldermen — 10/26/15 Page 25
In this case, we do just want to make clear tonight that without the support of the City, we don’t intend to move
forward in this direction with the developer. Like Melissa said, we want you to understand that this is a really
unique situation, this isn’t something we see all the time. We want to make very clear to you that this is, and |
hope we’ve done that tonight, that this is addressing more than just the Mohawk Tannery Site. It is addressing
these other parcels that otherwise would go untouched by EPA.
Special Bd. of Aldermen — 10/26/15 Page 24
other highlights here which are impacted, small impacted areas. The plan is to consolidate everything down
into the lagoon area, so essentially the three sites after will have no impact such that residential use could
occur. So it is really to get everything down to the smallest area possible where there will be a use restriction
and monitoring wells and deed restriction and keep it there rather than having it housed across the property.
Special Bd. of Aldermen — 10/26/15 Page 23
Ms. Taylor Yes you absolutely will get a response. Our process is to respond to the comments when we issue
the action memorandum, it is usually an appendix to the action memorandum which is a decision document.
And all of those questions and comments will be answered as part of that document.
Mr. Solomon That's all the questions | have, thank you.
REMARKS BY THE ALDERMEN
Alderman Dowd
Special Bd. of Aldermen — 10/26/15 Page 22
Special Bd. of Aldermen — 10/26/15 Page 21
Alderman Lopez
Special Bd. of Aldermen — 10/26/15 Page 20
Street Parkway or wherever, some pile of asbestos that also needs to be moved. So the proposal, as the
neighbors understand it, has not been to clean up the lagoons, it has been to add more to them and then cap
what is going on. There is a separate chamber that they are describing behind the two lagoons, but they also
had a plan to pile stuff higher on the secant wall if | understand correct.
Mr. Millan-Ramos Correct.
Alderman Lopez
Special Bd. of Aldermen — 10/26/15 Page 19
Alderman Klee
Actually | have two questions and again from Alderman O’Brien, when you said about the monitoring, basically
EPA kind of hands it over to DES so the State would do the monitoring or do you continue to do the monitoring.