Board Of Aldermen - Agenda - 5/25/2021 - P32
PRIORITY DEPARTMENTS PROJECTS DEPARTMENT C.1.C
REQUESTED RECOMMENDS
Division of Traffic Communication
A-3 Public Works & Detection Upgrades
(Streets) $ 145,000 $ 145,000
PRIORITY DEPARTMENTS PROJECTS DEPARTMENT C.1.C
REQUESTED RECOMMENDS
Division of Traffic Communication
A-3 Public Works & Detection Upgrades
(Streets) $ 145,000 $ 145,000
PRIORITY DEPARTMENTS PROJECTS DEPARTMENT C.1.C
REQUESTED RECOMMENDS
Division of City Wide Park and Playground
A-3 Public Works Improvements
(Park and Rec) $ 200,000 $ 200,000
PRIORITY DEPARTMENTS PROJECTS DEPARTMENT C.1.C
REQUESTED RECOMMENDS
A-2 Economic East Hollis Street & Bridge St
Development Intersection Improvements $ 183,050 $ 183,050
PRIORITY DEPARTMENTS PROJECTS DEPARTMENT C.1.C
REQUESTED RECOMMENDS
A-2 Fire Department Fire Station Alerting System
$ 500,000 $ 500,000
With increases in number of calls for service, Fire is in need of upgraded Fire Station Alerting systems to enable to
more efficiently process calls and create data to track NFPA compliance.
A-2 Communications Public Safety Portable Radio
Replacement $ 3,500,000 $ 3,500,000
PRIORITY DEPARTMENTS PROJECTS DEPARTMENT C.1.C
REQUESTED RECOMMENDS
Division of EDC-5 Safe Transportation
A-1 Public Works Every Pedestrian
(Engineering) Implementation $ 113,000 $ 113,000
The project involves the purchase and installation of rectangular rapid flashing beacons throughout the downtown
core. The implementation of these countermeasures will increase pedestrian safety. The City funds of $113,000 will
be a 20% match of Federal funds.
FY 2022 CAPITAL IMPROVEMENT PROJECTS
CITY OF NASHUA, NEW HAMPSHIRE
SHORT-TERM PROJECTS
“A”
SHORT-TERM PROJ ECTS: Programs/Projects that can be completed within a single year and that probably will be paid for
with cash from the City's Capital Budget. These projects may be in the six-digit, thousand-dollar range.
PRIORITY DEPARTMENTS PROJECTS DEPARTMENT C.1.C
REQUESTED RECOMMENDS
Division of Stadium Drive Facility
B-2 Public Works Heating System Upgrades
(Street Department) $ 2,000,000 $ 2,000,000
The estimated cost to replace the 1978 boiler is $2,000,000. The current heating system is obsolete and requires
extensive maintenance each year. The upgraded heating system would operate more efficiently requiring less
maintenance and would create a better working environment.
TOTAL FY 2022 LONG-TERM "B" PROGRAMS: $ 3,590,000 $ 3,590,000
“BRB”
B = Desirable (second priority): Programs/Projects which will benefit the community whose validity of planning and timing have
been established.
PRIORITY DEPARTMENTS PROJECTS DEPARTMENT C.I.C
REQUESTED RECOMMENDS
Division of Annual Drainage
B-1 Public Works Improvements
(Engineering) $ 75,000 $ 75,000
PRIORITY DEPARTMENTS PROJECTS DEPARTMENT C.1.C
REQUESTED RECOMMENDS
Division of Taylor Falls and
A-2 Public Works Veterans Bridges
(Engineering) Deck Rehabilitation $ 550,000 $ 550,000
FY 2022 CAPITAL IMPROVEMENT PROJECTS
CITY OF NASHUA, NEW HAMPSHIRE
LONG-TERM PROGRAMS
"A"
LONG-TERM PROGRAMS: Programs/Projects that will span more than one year from beginning to end, and that probably will
be bonded, over a period of years. These programs may be proposed in a phased approach with architectural and engineering work, for
example, being a first phase followed by construction in later phase(s). These programs may be in the seven-digit, million-dollar range.