Project Number: 228730 WWTEF SCADA Upgrades
Issue Date: AugustSeptember, 2017 Nashua, NH

SECTION 01 11 00
SUMMARY OF WORK

PART 1 — GENERAL
1.01 SECTION INCLUDES

A. Project Description

B. Description of the Work

C. Coordination and Sequencing
1.02 PROJECT DESCRIPTION

Finance Committee - Agenda - 11/15/2017 - P145

By dnadmin on Mon, 11/07/2022 - 10:18
  • Read more about Finance Committee - Agenda - 11/15/2017 - P145

A-3.3 (3)

1. Name of Bidder.

2. Permanent Main Office address.

3. When organized?

4. Where incorporated?

5. Is bidder registered with the Secretary of the State to do business in New Hampshire?

6. For how many years has your firm engaged in the contracting business under its present name?
Also state names and dates of previous firm names, if any.

7. Contracts on hand. (Schedule these, showing gross amount of each contract and the
approximate anticipated dates of completion.)

Finance Committee - Agenda - 11/15/2017 - P144

By dnadmin on Mon, 11/07/2022 - 10:18
  • Read more about Finance Committee - Agenda - 11/15/2017 - P144

A-3.2 (3)

BIDDER acknowledges receipt of the following ADDENDUM:

BASE BID: BIDDER agrees to perform all the work described in the CONTRACT DOCUMENTS for
the following LUMP SUM PRICE excluding Alternate 1

Dollars and Cents §$
(Use words) (Use figures)

ALTERNATE 1: BIDDER agrees to replace ceiling in thickening room with ceiling tiles
as specified in Section 09 51 00 and as indicated in the General Notes on Drawing E-003
for the following LUMP SUM PRICE

Dollars and Cents $
(Use words) (Use figures)

Finance Committee - Agenda - 11/15/2017 - P143

By dnadmin on Mon, 11/07/2022 - 10:18
  • Read more about Finance Committee - Agenda - 11/15/2017 - P143

C-2.8 (3)

The use of any such term or adjective is not intended to and shall not be effective
to assign to Engineer any duty or authority to supervise or direct the performance
of the Work, or any duty or authority to undertake responsibility contrary to that
above or any other provision of the Contract Documents.

SC-55 Pre-Construction Conference
ADD the following at the end of the paragraph.sentences=

“and conducted in accordance with the General Requirements, Paragraph 1.03.A.6.

Finance Committee - Agenda - 11/15/2017 - P142

By dnadmin on Mon, 11/07/2022 - 10:18
  • Read more about Finance Committee - Agenda - 11/15/2017 - P142

C-2.6.(3)

consultants, contractors, or subcontractors. The only contractual relationship created by this
agreement is between the Owner and Contractor, and nothing in this agreement shall create any
contractual relationship between the Owner and Contractor’s consultants, sub consultants,
contractors or subcontractors. The parties also agree that Contractor is not a City employee and
that there shall be no:

Finance Committee - Agenda - 11/15/2017 - P141

By dnadmin on Mon, 11/07/2022 - 10:18
  • Read more about Finance Committee - Agenda - 11/15/2017 - P141

C-2.5.(3)

Neither party shall be considered in default of the performance of its obligations hereunder to the
extent that performance of such obligations is prevented or delayed by any cause, existing or
future, which is beyond the reasonable control of such party. Delays arising from the actions or
inactions of one or more of Contractor’s principals, officers, employees, agents, subcontractors,
consultants, vendors, or suppliers are expressly recognized to be within Contractor’s control.

SC-23 Construction Schedule and Periodic Estimates

Finance Committee - Agenda - 11/15/2017 - P140

By dnadmin on Mon, 11/07/2022 - 10:18
  • Read more about Finance Committee - Agenda - 11/15/2017 - P140

A-2.2 (3)

A PERFORMANCE BOND and a PAYMENT BOND, each in the amount of one hundred percent
(100%) of the CONTRACT PRICE, with a corporate surety approved by the OWNER, will be
required for the faithful performance of the contract.

Attorneys-in-fact who sign BID BONDS or PAYMENT BONDS and PERFORMANCE BONDS
must file with each BOND a certified and effective dated copy of their power of attorney.

Finance Committee - Agenda - 11/15/2017 - P139

By dnadmin on Mon, 11/07/2022 - 10:18
  • Read more about Finance Committee - Agenda - 11/15/2017 - P139

A-2.1 (3)

INFORMATION FOR BIDDERS

BIDS will be received by the City of Nashua, New Hampshire (herein called the "OWNER"), at
Central Purchasing, 229 Main Street, Room 128, Nashua NH 0306luntil 3:00PM on Tuesday

October 10, 2017 Monday-October2,2017 and then at said office publicly opened and read aloud.

Each BID must be submitted in a sealed envelope, addressed to:
Central Purchasing, 229 Main Street, Room 128, Nashua NH 03061

Finance Committee - Agenda - 11/15/2017 - P138

By dnadmin on Mon, 11/07/2022 - 10:18
  • Read more about Finance Committee - Agenda - 11/15/2017 - P138

A-1.1 (3)

ADVERTISEMENT FOR BIDS

City of Nashua, New Hampshire

Owner

229 Main Street, Nashua, New Hampshire 03061
Address

Finance Committee - Agenda - 11/15/2017 - P137

By dnadmin on Mon, 11/07/2022 - 10:18
  • Read more about Finance Committee - Agenda - 11/15/2017 - P137

DIVISION 01 - GENERAL REQUIREMENTS Page No. through Page No.

011100 Summary of Work 01 11 00-1 01 11 00-2
011105 Overall General Requirements O01 11 05-1 01 11 05-26
Forms Attached

Submittal Transmittal (Form C-00 62 11)

Application for Payment (Form C-00 62 76)

Request for Interpretation/Information (Form C-00 63 15)
Field Order (Form C-00 63 36)

Work Change Directive (Form C-00 63 49)

Change Request (Form C- 00 63 60)

Notice of Substantial Completion (Form C-00 65 15)
Notice of Completion (Form C-00 65 18)