Finance Committee - Agenda - 11/15/2017 - P256
Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August 2017 Nashua, NH
SECTION 01 11 05
OVERALL GENERAL REQUIREMENTS
PART 1-— GENERAL
1.01 SUMMARY
Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August 2017 Nashua, NH
SECTION 01 11 05
OVERALL GENERAL REQUIREMENTS
PART 1-— GENERAL
1.01 SUMMARY
Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August, 2017 Nashua, NH
1.04 COORDINATION AND SEQUENCING
A. Coordination
1. Ensure that facilities and wastewater system flows are maintained and
remain in service at all times unless otherwise approved.
a. Obtain written approval of Owner for shutdowns. Notify Engineer a
minimum of two weeks prior to any required shutdowns.
b. Prepare a Shutdown Plan for each requested shutdown indicating
what existing valves must be operated by Owner personnel during
the shutdown.
Project Number: 228730
WWTE SCADA Upgrades
Issue Date: August, 2017 Nashua, NH
SECTION 01 11 00
SUMMARY OF WORK
PART 1 —- GENERAL
1.01 SECTION INCLUDES
A. Project Description
B. Description of the Work
C. Coordination and Sequencing
1.02 PROJECT DESCRIPTION
A.
This page intentionally left blank
Project Number: 228730 WWTFE SCADA Upgrades
Issue Date: August 2017 Nashua, NH
SECTION 00 01 07
SEALS PAGE
The engineering material and data contained in these Contract Documents were prepared under
the supervision and direction of the undersigned, whose seal as registered professional engineer
is affixed below.
Aususk 2%, 2017
Date of Issue
SS WeEWw Hay Uy
Jorfathon Grant, P.E.
Woodard & Curran, Inc. (Engineer)
SEALS PAGE
WOODARD & CURRAN 00 01 07-1
C-2.8
The use of any such term or adjective is not intended to and shall not be effective
to assign to Engineer any duty or authority to supervise or direct the performance
of the Work, or any duty or authority to undertake responsibility contrary to that
above or any other provision of the Contract Documents.
SC-55 Pre-Construction Conference
ADD the following sentences:
“The Contractor shall attend a biweekly construction meeting and be prepared to outline the
C-2.7
ADD the following:
33.3
The Project has been designed by Woodard and Curran, Inc. referred to as the
4.
5.
6.
C-2.6
Participation in group insurance plans which may be available to employees of the
Owner;
Participation or contributions by either the Contractor or the Owner to the public
employees retirement system;
Accumulation of vacation leave or sick leave provided by the Owner;
Unemployment compensation coverage provided by the Owner.
C-2.5
Neither party shall be considered in default of the performance of its obligations hereunder to the
extent that performance of such obligations is prevented or delayed by any cause, existing or
future, which is beyond the reasonable control of such party. Delays arising from the actions or
inactions of one or more of Contractor’s principals, officers, employees, agents, subcontractors,
consultants, vendors, or suppliers are expressly recognized to be within Contractor’s control.
C-2.4
Upon receipt of notice of termination for cause, Contractor shall:
1. Immediately discontinue work on the date and to the extent specified in the notice.
2. Provide the Owner with a list of all unperformed services.
3. Place no further orders or sub-contracts for materials, services, or facilities, other than as
may be necessary or required for completion of such portion of work under the contract that is
not terminated.