Finance Committee — 12/01/2021 Page 20
MOTION BY ALDERMAN HARRIOTT-GATHRIGHT TO ACCEPT, PLACE ON FILE AND APPROVE THE PURCHASE
OF ONE (1) 2021 TORO GM5910 GROUNDMASTER MOWER FROM TURFPRODUCTS OF ENFIELD,
CONNECTICUT, OFF THE SOURCEWELL CONTRACT -— 64117 FOR THE PRICE OF $137,537.19. ADDITIONALLY,
APPROVE THE PURCHASE AND INSTALLATION OF RADIO SYSTEM FROM MOTOROLA SOLUTIONS, INC., IN AN
AMOUNT NOT TO EXCEED $5,000. FUNDING WILL BE THROUGH DEPARTMENT 177 PARK AND RECREATION;
FUND: TRUST; ACTIVITY: CERF, BY ROLL CALL
ON THE QUESTION
Jonathan Ibarra, Superintendent of Streets
Thank you, Mr. Mayor. So this tractor or mower will be replacing 14452 which I've learned is the backbone of the Park
and Rec Department’s mowing operations. Also learned that there's 40 parks consisting of 900 acres of which 150 acres
is mowed and this does the majority of that mowing. When this breaks down, they have to send out a fleet of smaller
mowers and it really hurts their production. So this is a key piece in the Park and Rec grounds maintenance area. Any
questions?
Mayor Donchess
Any questions? Madam Clerk please call the roll.
A viva voce roll call was taken which resulted as follows:
Yea: Alderman Klee, Alderman Harriott-Gathright, Alderwoman Kelly,
Alderman Laws, Alderman O’Brien, Mayor Donchess 6
Nay: 0
MOTION CARRIED
From: Kelly Parkinson, Purchasing Manager
Re: Water Pump Rebuild in the amount not to exceed $50,073 funded from accounts 54487 Equipment Repairs &
Maintenance/Wastewater Fund (Wastewater)
MOTION BY ALDERMAN HARRIOTT-GATHRIGHT TO ACCEPT, PLACE ON FILE AND APPROVE THE REBUILD OF
A RAW WATER PUMP BY WILLIAMSON PUMP & MOTOR OF EPPING, NH, IN THE AMOUNT OF $50,072.15.
FUNDING WILL BE THROUGH DEPARTMENT 169 WASTEWATER; ACCOUNT CLASSIFCATION: 54 PROPERTY
SERVICES; FUND: 54487 EQUIPMENT REPAIRS & MAINTENANCE/WASTEWATER FUND, BY ROLL CALL
ON THE QUESTION
Mayor Donchess
Who's here on this?
David Boucher, Superintendent of Wastewater
lam Mayor. David Boucher, Wastewater Superintendent.
Mayor Donchess
Yeah go ahead.
David Boucher, Superintendent of Wastewater
The Wastewater Department had sent out a failed motor to a 20 million gallons per day pump to Williamson Pump for
inspection. It had failed due to water getting in the motor cavity. So this cost will cover the entire rebuild of the motor, the
rewinding, the baking, and the reassembly with factory parts, and new power cables.