City of Nashua, Public Works Division
Board of Public Works Meeting Date: December 17, 2020
Jeff Lafleur, Superintendent
Solid Waste Department
Phase IV Landfill Permit Application —- Response to NHDES Comments
To approve services from Sanborn Head & Associates, Inc. (SHA), of Concord,
NH in an amount of $30,000 to address New Hampshire Department of
Environmental Services (NHDES) comments to the Type 1A permit application
for the proposed Phase IV secure landfill expansion. Funding will be through
Department: 168 Solid Waste; Fund: Solid Waste; Activity: Expansion Phase 3
and 4.
The NHDES has completed their initial review of the Type 1A permit application
submitted by the City in July 2020 for Phase IV of the secure landfill expansion.
In correspondence to the City dated November 20, 2020, the NHDES requests
additional information in order to deem the application complete. The Solid
Waste Department is requesting $30,000 for SHA to address the request for
additional information. Once deemed complete, NHDES will begin a technical
review of the permit application. When that process begins additional funding for
SHA will be required at that time to address comments from the technical review
and to continue the permitting process.