CHANGE ORDER
No.1
PROJECT: WATER QUALITY TESTING AND MONITORING
OWNER’S CONTRACT NO: RFP0931-060818
EXECUTED CONTRACT DATE: August 13, 2018
DATE OF ISSUANCE: _Upon City Approval EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 157523
VENDOR:: Chemserve Environmental Analysis
You are directed to make the following changes in the Contract Documents:
Description: After the execution of a 3-year contract with Chemserve Environmental, the testing scope of
work changed due to increase testing requirements, established by New Hampshire Environmental
Services (NHDES) went into effect, especially for Per and PolyFlucroAlkyl Substances (PFAS) Testing.
Justification: In order to complete the remainder of FY21 required Groundwater and Leachate Sampling;
an additional $29,888 will be needed.
e Chemserve Environmental has submitted a revised timeline scope of work, which is attached and
made part of this Change Order, in the amount of $19,118.
e Additional funds are also necded to make payment on the balance of an invoice duc to Chemserve
Environmental, in the amount of $10,770.
Change Order # 1 lof?
RFP093 1-060818
WATER QUALITY TESTING AND MONITORING