GUARDIAN
ENERGY MANAGEMENT SOLUTIONS
April 19, 2021
Sarah Marchant
Community Development Director
City of Nashua
229 Main St.
Nashua, NH 063060
Subject: Nashua Riverwalk Lighting Change Order
Dear Sarah,
Following up on our conversation regarding the project scope the following table provides a summary of the scope
additions and deletions. Item 3, represents the additional cost of running the power circuit that was originally
specified to be powered from the south side of the river via pedestal EX2 which is no longer in scope.
1) Removal of lighting poles @ eastern most section of Riverwalk - 5 poles. ($43,287.00)
2) Installation of dimming capability at Cotton Transfer bridge to allow control of new
fixtures. Includes labor and materials to install two new control circuits to allow $11,812.00
dimming.
3) Re-alignment of west side Cotton Bridge and pole power circuits. Includes new labor $21,937.00
and materials to install new conduit and wire from existing pedestal EX1
Net Change Order Amount ($9,538.00)
Please let me know if you have any questions.
Thank you,
Tom Schnare
Lighting Installation Manager
781-560-3882
Accepted:
Signature Date
Printed Name & Title
Guardian Energy Management Solutions™
420 Northboro Road Central, Marlborough, MA 01752 | Phone: 508-597-1333 | MA Electrical License 883A1 | www.guardian-energy.com