Jim Donchess
Mayor e City of Nashua
To: Finance Committee
From: Jim Donchess
Date: April 28, 2021
Re: Change Order for Riverfront Lighting Change Order #1
In accordance with O-14-011, communication of amendments to contracts, this memo is to inform
the Finance Committee of a subsequent change order to the request from the Community
Development Division for the Riverfront Lighting Project.
The original contract price in the amount of $607,781 was approved by Finance Committee on
October 21, 2020.
The Community Development Division has requested a reduction in the amount of $9,538.00 to
accommodate the following changes:
Removal of 5 lighting poles from original plan ($43,287)
Additionof dimming capability at Cotton Transfer Bridge $11,812
Realignment of West Side Cotton Bridge and Pole Power Circuits $21,937
Total of Changes Requested ($9,538)
These changes decrease the approved total from $607,781 to $598,243.