18/2018
®
af A
SOLUTIONS
SECTION 3
IMPLEMENTATION PLAN
3.1 STATEMENT OF WORK
Motorola will install and configure the proposed equipment. The following table describes the tasks involved with
installation and configuration.
Contract Finalization and Team Creation
Execute contract and distribute contract documents.
Assign a Project Manager as a single point of contact.
Assign resources.
Schedule project kickoff meeting.
Deliverable: Signed contract, defined project team, and scheduled project kickoff meeting.
Project Kickoff
Introduce team, review roles, and decision authority.
Present project scope and objectives.
Review SOW responsibilities and project schedule.
Schedule Design Review.
Deliverable: Completed project kickoff and scheduled Design Review.
Design Review
Present the system design and operational requirements for the solution.
Present installation plan.
Present preliminary cutover plan and methods to document final cutover
process.
Present configuration and details of sites required by system design.
Validate that customer sites can accommodate proposed equipment.
Provide approvals required to add equipment to proposed existing sites.
Review site safety, security, and access procedures.
Finalize site acquisition and development plan.
Review safety rules and procedures.
Present equipment layout plans and system design drawings.
Provide backhaul performance specifications and demarcation points.
Provide heat load and power requirements for new equipment.
Provide information on existing system interfaces.
Use or disclosure of this proposal is subject
to the restrictions on the disclosure page.
Motorola
Solutions
SSSR S
GVV8*G
O98
OPVG@VGRVDGOOGNGDNsB B
TLELLLEELTLL LETT TTL LUT ETAL ne eee eereeree teresa Es TUi li da di LL
OO08
O000
YVO0OOO008000 000
PCCP PETERS OPE ER EEE TTA ERR ETAT EE ee ee ee POR EOPOR ETOP EPEAT ETAT EEC EERE ROTTER EEE
Page 18