Finance Committee - 6/7/2017 Page 4
Alderman Caron
Right, that’s another issue and | appreciate that.
Mayor Donchess
There continues to be EPA and DES issues. We are operating pursuant to a court order, the so-called
Consent Decree. There continues to be issues that they raise, and they probably won't stop raising issues.
We can expect, | think, that we will continue to work on this system regularly for quite some time.
Alderman Siegel
The digester is going to be cleaned so that’s going to be a big job. It’s huge; wait until that comes up.
From: Dan Kooken, Purchasing Manager
Re: Contract For Waste Water Facility Energy Audit (Value: $22,800)
MOTION BY ALDERMAN SIEGEL TO ACCEPT, PLACE ON FILE AND AWARD THE CONTRACT
TO PROCESS ENERGY SERVICES, LLC, IN THE AMOUNT OF $22,800. FUNDS ARE AVAILABLE
IN DEPARTMENT 169, WASTEWATER, NH DES ENERGY AUDIT GRANT
MOTION CARRIED
From: Dan Kooken, Purchasing Manager
Re: Headworks Upgrade Project — Change Order #4 (Value: $27,625)
MOTION BY ALDERMAN SIEGEL TO ACCEPT, PLACE ON FILE AND AUTHORIZE CHANGE ORDER #4
TO THE CONTRACT WITH T-BUCK CONSTRUCTION, INC. IN THE AMOUNT OF $27,625. SOURCE OF
FUNDING IS DEPARTMENT 169, WASTEWATER; STATE REVOLVING FUND LOAN, HEADWORKS
UPGRADE
MOTION CARRIED
From: Dan Kooken, Purchasing Manager
Re: Contract Extension for Single Stream Recycling (Value: $249,925)
MOTION BY ALDERMAN SIEGEL TO ACCEPT, PLACE ON FILE AND AUTHORIZE THE CONTRACT
EXTENSION WITH CASELLA RECYCLING, LLC, IN THE AMOUNT OF $249,925. FUNDS ARE
AVAILABLE IN DEPARTMENT 168, SOLID WASTE
MOTION CARRIED
From: Dan Kooken, Purchasing Manager
Re: FY18 Contract Extension for Purchase of B5 Biodiesel Fuel for Nashua Transit (Value: $130,000)
MOTION BY ALDERMAN SIEGEL TO ACCEPT, PLACE ON FILE AND AUTHORIZE THE CONTRACT
EXTENSION WITH EAST RIVER ENERGY IN THE AMOUNT OF $130,000. SOURCE OF FUNDING IS
DEPARTMENT 186 , TRANSPORTATION; FTA GRANT
MOTION CARRIED
UNFINISHED BUSINESS — None
NEW BUSINESS — None