Summary
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times
$48,600 Substantial completion: Oct 15, 2019
Ready for final payment: Oct 31, 2019
Net changes from previous Change Orders Net change from previous Change Orders
Change Order 1 $ 22,800
Change Order 2 $ 94,400
Change Order 3 $100,500
$217,700 730 Days
Contract Price prior to this Change Order Contract Times prior to this Change Order
$266,300 Substantial completion: Oct 15, 2021
Ready for final payment: Oct 31, 2021
Net Increase (decrease) of this Change Order Net Increase (decrease) of this Change Order
$ 63,795 365 Days
Contract Price with all approved Change Orders Contract Times with all approved Change Orders
$330,095 Substantial completion: Oct 15, 2022
Ready for final payment: Oct 31, 2022
RECOMMENDED: ACCEPTED: APPROVED:
By: By: By:
Daniel Hudson, DPW Jason G. Richard, CFO Mayor Jim Donchess
City Engineer S.W. Cole Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: Date: Date:
Change Order #4 2 of 2
2019 Asphalt Testing