¥ Data Collection guidelines have been completed. Lister's information has been completed
and the police department has been informed of all aspects of the data collection phase
of the revaluation.
M
Data entry will be ongoing throughout the project, commencing after June 2020.
v¥ Usernames and passwords have been assigned and will have people associated with them
do the data entry.
v Daily communication with the Assessor's office is on-going concerning the progress of the
data collection as well as any issues to be addressed.
Interior Inspection are ongoing. More schedules will be added as needed.
Ward 1-9 Property record cards have been printed.
Images are being taken and will coincide with production numbers.
NS] NESTS
Images are also being captured to the live database.
Y Data entry is on-going.
Y The database is live in Nashua NH
WARD DATA COLLECTION
Ward 1 Count 3,869
Ward 2 Count 3,478
Ward 3 Count 2,845
Ward 4 Count 2,287
Ward 5 Count 4,480
Ward 6 Count 3,035
Ward 7 Count 3,027
Ward 8 Count 2,764
Ward 9 Count 3,521
The Following is the Measure and Listing Numbers Accountable as of November 6", 2021:
Total Residential Improved Parcel Count 25,605
Measures 24,871
Total Interior Inspections 1,686
Refusals to Date — Partial/Full 7/300
Total Measures with Refusal 25,171
Total Percent Complete Measured 98%