TIMELINE
Construction Documents through Occupancy
e Present updates to Joint Committee on Public Works and Infrastructure
e Coordinate with Harvey Construction to remain on budget
e Schedule for completion of documents + construction
e Design Development thru Construction Documents: Total of 24 weeks —- end of 2021
e Coordinate work of design team: Civil, Landscape, Structural, MEP/FP + Code
e Updates to estimate
e Coordinate with City Boards as needed to obtain permits
Bidding: 4-6 weeks; expected mid-November through December 2021
January through March 2022: Shop Drawing Review
Construction: Spring Start - 10 months
Occupancy: Early 2023