Finance Committee - Agenda - 3/17/2021 - P147
B.10 TAX CS eee ccceecccceeececceeeecceseeecceeeeesseeeeeeesesseeeesseeecseaeescsseenssseeseseesssnesessenessesnnsceseessssesseseesssatesssseneestegs 26
B.10 TAX CS eee ccceecccceeececceeeecceseeecceeeeesseeeeeeesesseeeesseeecseaeescsseenssseeseseesssnesessenessesnnsceseessssesseseesssatesssseneestegs 26
TABLE OF CONTENTS
FOR
GENERAL CONDITIONS
Page
DIVISION 5
GENERAL CONDITIONS
Address for giving notices to Owner:
Mark Saunders, Senior Staff Engineer
Division of Public Works
Engineering Department
9 Riverside Street
Nashua, NH 03062
IN WITNESS WHEREOF, OWNER and
Address for giving notices to Contractor:
Robert Bushnell, President
Sunshine Paving Corporation
29 Constitution Drive
Hudson, NH 03051
CONTRACTOR have signed this Agreement in triplicate. One counterpart
each has been delivered to OWNER, CONTRACTOR and ENGINEER. All portions of the Contract Documents have
d. City of Nashua, Standard Specifications for Road Construction, Approved and Adopted
June 11, 1986, incorporated by reference;
e. City of Nashua, Standard Specifications for Sidewalk Construction, Approved and
Adopted August 28, 1995, incorporated by reference; and
f. City of Nashua Ordinance O-03-219 (Amended), Approved November 14, 2003.
ARTICLE 9 - MISCELLANEOUS
9.01 Terms
A. Terms used in this will have the meanings indicated in the General Conditions.
9.02. Assignment of Contract
E. CONTRACTOR has obtained and carefully studied (or assumes responsibility for having done so)
all additional or supplementary examinations, investigations, explorations, tests, studies, and data concerning
conditions (surface, subsurface and Underground Facilities) at or contiguous to the Site which may affect cost,
progress, or performance of the Work or which relate to any aspect of the means, methods, techniques,
sequences and procedures of construction, if any, expressly required by the Contract Documents to be employed
the OWNER. The principal will be held by the bank, available only to the OWNER, until
termination of the contract.
2. Until the work is 50% complete, as determined by the ENGINEER, retainage shall be 10%
of the monthly payments claimed. The computed amount of retainage will be deposited
in the escrow account established above.
B. as provided in paragraph 11.03 of the General Conditions estimated quantities are not
guaranteed, and determinations of actual quantities and classification are to be made by ENGINEER as provided
in paragraph 9.08 of the General Conditions. Unit prices have been computed as provided in paragraph 11.03
of the General Conditions.
ARTICLE 6 - PAYMENT PROCEDURES
6.01 Submittal and Processing of Payments
4.02 Dates for Substantial Completion and Final Payment
The anticipated Commencement date for the contract is on or about March 22, 2021. Project will begin
once a written “Notice to Proceed” is issued.
Substantial Completion shall be by October 15, 2021. Substantial completion is defined in Section 1.01 of
the General Terms and Conditions.
Contract completion shall be by October 31, 2021.
4.03 Liquidated Damages
STANDARD FORM OF AGREEMENT
BETWEEN OWNER AND CONTRACTOR
THIS AGREEMENT is dated as of the day of in the year 2021 by and between the
City of Nashua, New Hampshire (hereinafter called OWNER) and __Sunshine Paving Corporation
and its successors, transferees and assignees together hereinafter called CONTRACTOR).
OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as
follows: