assembled by the Contractor pursuant to Section 9.10; and issue a final Certificate for Payment pursuant to Section
9.10.

§ 4.2.10 If the Owner and Architect agree, the Architect will provide one or more project representatives to assist in
catrying, out the Architect’s responsibilities at the site. The duties, responsibilities and limitations of authority of
such project representatives shall be as set forth in an exhibit to be incorporated in the Contract Documents.

Finance Committee - Agenda - 12/4/2019 - P67

By dnadmin on Mon, 11/07/2022 - 13:00
  • Read more about Finance Committee - Agenda - 12/4/2019 - P67

§ 4.2.2 The Architect will visit the site at intervals appropriate to the stage of construction, or as otherwise agreed
with the Owner, to become generally familiar with the progress and quality of the portion of the Work completed,
and to determine in general if the Work observed is being performed in a manner indicating that the Work, when
fully completed, will be in accordance with the Contract Documents. However, the Architect will not be required to

Finance Committee - Agenda - 12/4/2019 - P66

By dnadmin on Mon, 11/07/2022 - 13:00
  • Read more about Finance Committee - Agenda - 12/4/2019 - P66

§ 3.15.2 If the Contractor fails to clean up as provided in the Contract Documents, the Owner may do so and Owner
shall be entitled to reimbursement from the Contractor.

§ 3.16 ACCESS TO WORK
The Contractor shall provide the Owner and Architect access to the Work in preparation and progress wherever
located.

§ 3.17 ROYALTIES, PATENTS AND COPYRIGHTS

Finance Committee - Agenda - 12/4/2019 - P65

By dnadmin on Mon, 11/07/2022 - 13:00
  • Read more about Finance Committee - Agenda - 12/4/2019 - P65

§ 3.12.8 The Work shall be in accordance with approved submittals except that the Contractor shall not be relieved of
responsibility for deviations from requirements of the Contract Documents by the Architect’s approval of Shop
Drawings, Product Data, Samples or similar submittals unless the Contractor has specifically informed the Architect
in writing of such deviation at the time of submittal and (1) the Architect has given written approval to the specific

Finance Committee - Agenda - 12/4/2019 - P64

By dnadmin on Mon, 11/07/2022 - 13:00
  • Read more about Finance Committee - Agenda - 12/4/2019 - P64

current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the
Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall
provide for expeditious and practicable execution of the Work.

Finance Committee - Agenda - 12/4/2019 - P63

By dnadmin on Mon, 11/07/2022 - 13:00
  • Read more about Finance Committee - Agenda - 12/4/2019 - P63

Contract Documents, the Contractor shal] promptly provide notice to the Owner and the Architect before conditions
are disturbed and in no event later than 21 days after first observance of the conditions. The Architect will promptly
investigate such conditions and, if the Architect determines that they differ materially and cause an increase or
decrease in the Contractor’s cost of, or time required for, performance of any part of the Work, will recommend an

Finance Committee - Agenda - 12/4/2019 - P62

By dnadmin on Mon, 11/07/2022 - 13:00
  • Read more about Finance Committee - Agenda - 12/4/2019 - P62

methods, techniques, sequences or procedures may not be safe, the Contractor shall give timely written notice to the
Owner and Architect and shall not proceed with that portion of the Work without further written instructions from
the Architect.

§ 3.3.2 The Contractor shall be responsible to the Owner for acts and omissions of the Contractor’s employees,
Subcontractors and their agents and employees, and other persons or entities performing portions of the Work for, or
on behalf of, the Contractor or any of its Subcontractors.

Finance Committee - Agenda - 12/4/2019 - P61

By dnadmin on Mon, 11/07/2022 - 13:00
  • Read more about Finance Committee - Agenda - 12/4/2019 - P61

or failure. If payments then or thereafter due the Contractor are not sufficient to cover such amounts, the Contractor
shall promptly pay the difference to the Owner.

ARTICLE 3 CONTRACTOR

§ 3.1 GENERAL

Finance Committee - Agenda - 12/4/2019 - P60

By dnadmin on Mon, 11/07/2022 - 13:00
  • Read more about Finance Committee - Agenda - 12/4/2019 - P60

ARTICLE 2 OWNER

§ 2.1 GENERAL

§ 2.1.1 The Owner is the person or entity identified as such in the Agreement and is referred to throughout the
Contract Documents as if singular in number. The Owner shall designate in writing a representative who shall have
express authority to bind the Owner with respect to all matters requiring the Owner’s approval or authorization.
Except as otherwise provided in Section 4.2.], the Architect does not have such authority. The term “Owner” means
the Owner or the Owner’s authorized representative.

Finance Committee - Agenda - 12/4/2019 - P59

By dnadmin on Mon, 11/07/2022 - 13:00
  • Read more about Finance Committee - Agenda - 12/4/2019 - P59

§ 1.1.6 THE SPECIFICATIONS
The Specifications are that portion of the Contract Documents consisting of the written requirements for materials,
equipment, systems, standards and workmanship for the Work, and performance of related services.

§ 1.1.7 INSTRUMENTS OF SERVICE