6.12 Record Documents
A. CONTRACTOR shall maintain in a safe place at the Site one record copy of all Drawings, Specifications,
Addenda, Written Amendments, Change Orders,
6.12 Record Documents
A. CONTRACTOR shall maintain in a safe place at the Site one record copy of all Drawings, Specifications,
Addenda, Written Amendments, Change Orders,
I. If blasting or use of explosives is necessary for prosecution of Work, the CONTRACTOR shall provide the
ENGINEER with a blasting plan in compliance with OSHA, State, and local regulations, laws, ordinances, and
requirements. CONTRACTOR shall exercise the utmost care not to endanger life or property. CONTRACTOR shall
be responsible for all damage resulting from the use of explosives. CONTRACTOR shall notify each property
OWNER and utility company having structures or facilities in proximity to the site of the work of its intentions to use
Risk Management
City of Nashua
229 Main Street
Nashua, NH 03060
6.09 Laws and Regulations
A. CONTRACTOR shall give all notices and comply with all Laws and Regulations applicable to the performance of
the Work. Except where otherwise expressly required by applicable Laws and Regulations, neither OWNER nor
ENGINEER shall be responsible for monitoring CONTRACTOR’s compliance with any Laws or Regulations.
any such Subcontractor, Supplier, or other individual or entity except as may otherwise be required by Laws and
Regulations.
D. CONTRACTOR shall be solely responsible for scheduling and coordinating the Work of Subcontractors,
Suppliers, and other individuals or entities performing or furnishing any of the Work under a direct or indirect contract
with CONTRACTOR.
E. CONTRACTOR shall require all Subcontractors, Suppliers, and such other individuals or entities performing or
furnishing any of the Work to communicate with ENGINEER through CONTRACTOR.
B. Substitute Construction Methods or Procedures:. If a specific means, method, technique, sequence, or procedure
of construction is shown or indicated in and expressly required by the Contract Documents, CONTRACTOR may
furnish or utilize a substitute means, method, technique, sequence, or procedure of construction approved by
ENGINEER. CONTRACTOR shall submit sufficient information to allow ENGINEER, in ENGINEER’s sole
discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract
6.05 Substitutes and “Or-Equals”
B. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent
thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during
regular working hours, and CONTRACTOR will not permit overtime work or the performance of Work on Saturday,
Sunday, or any legal holiday without OWNER’s written consent (which will not be unreasonably withheld) given after
prior written notice to ENGINEER.
B. CONTRACTOR shall be responsible for any deductible or self-insured retention. The nsk of loss within the
identified deductible amount will be borne by CONTRACTOR, Subcontractors, or others suffering any such loss, and
if any of them wishes property insurance coverage within the limits of such amounts, each may purchase and maintain
it at the purchaser’s own expense. OWNER shall not be responsible for purchasing and maintaining any property
insurance specified in this paragraph 5.06 to protect the interests of CONTRACTOR, Subcontractors, or others in the
coverage. The City may, at any time, order the contractor to stop work, suspend the contract or terminate the
contract for non-compliance. All subcontractors are subject to the same insurance requirements as the contractor.
3. Include completed operations insurance;
4. Include contractual liability insurance covering CONTRACTOR’s indemnity obligations under paragraphs 6.07,
6.11, and 6.20;