Documents and applicable Laws and Regulations, but during any such appeal, CONTRACTOR shall carry on the
Work and adhere to the progress schedule as provided in paragraph 6.18.A.

10.04 Notification to Surety

Finance Committee - Agenda - 2/1/2017 - P182

By dnadmin on Mon, 11/07/2022 - 10:28
  • Read more about Finance Committee - Agenda - 2/1/2017 - P182

B. ENGINEER will not supervise, direct, control, or have authority over or be responsible for CONTRACTOR's
means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident
thereto, or for any failure of CONTRACTOR to comply with Laws and Regulations applicable to the performance of
the Work. ENGINEER will not be responsible for CONTRACTOR's failure to perform the Work in accordance with
the Contract Documents.

Finance Committee - Agenda - 2/1/2017 - P181

By dnadmin on Mon, 11/07/2022 - 10:28
  • Read more about Finance Committee - Agenda - 2/1/2017 - P181

by a Field Order and will be binding on OWNER and also on CONTRACTOR, who shall perform the Work involved
promptly. If OWNER and CONTRACTOR are unable to agree on entitlement to or on the amount or extent, if any, of
any adjustment in the Contract Price or Contract Times, or both, as a result of a Field Order, a Claim may be made
therefore as provided in paragraph 10.05.

9.06 Rejecting Defective Work

Finance Committee - Agenda - 2/1/2017 - P180

By dnadmin on Mon, 11/07/2022 - 10:28
  • Read more about Finance Committee - Agenda - 2/1/2017 - P180

A. If and to the extent OWNER has agreed to furnish CONTRACTOR reasonable evidence that financial
arrangements have been made to satisfy OWNER's obligations under the Contract Documents, OWNER's
responsibility in respect thereof will be as set forth in the Supplementary Conditions.

ARTICLE 9 - ENGINEER'S STATUS DURING CONSTRUCTION

9.01 OWNER’s Representative

Finance Committee - Agenda - 2/1/2017 - P179

By dnadmin on Mon, 11/07/2022 - 10:28
  • Read more about Finance Committee - Agenda - 2/1/2017 - P179

A. Except as otherwise provided in these General Conditions, OWNER shall issue all communications to
CONTRACTOR through ENGINEER.
8.02 Replacement of ENGINEER

A. In case of termination of the employment of ENGINEER, OWNER shall appoint and whose status under the
Contract Documents shall be that of the former ENGINEER.

8.03 Furnish Data
A. OWNER shall promptly furnish the data required of OWNER under the Contract Documents.
8.04 Pay Promptly When Due

Finance Committee - Agenda - 2/1/2017 - P178

By dnadmin on Mon, 11/07/2022 - 10:28
  • Read more about Finance Committee - Agenda - 2/1/2017 - P178

ARTICLE 7 - OTHER WORK

7.01 Related Work at Site

A. OWNER may perform other work related to the Project at the Site by OWNER’s employees, or let other direct
contracts therefore, or have other work performed by utility Owner’s. If such other work is not noted in the Contract
Documents, then:

1. Written notice thereof will be given to CONTRACTOR prior to starting any such other work; and

Finance Committee - Agenda - 2/1/2017 - P177

By dnadmin on Mon, 11/07/2022 - 10:28
  • Read more about Finance Committee - Agenda - 2/1/2017 - P177

1. Abuse, modification, or improper maintenance or operation by persons other than CONTRACTOR,
Subcontractors, Suppliers, or any other individual or entity for whom CONTRACTOR is responsible; or

2. Normal wear and tear under normal usage.

Finance Committee - Agenda - 2/1/2017 - P176

By dnadmin on Mon, 11/07/2022 - 10:28
  • Read more about Finance Committee - Agenda - 2/1/2017 - P176

d. CONTRACTOR shall also have reviewed and coordinated each Shop Drawing or Sample with other Shop
drawings and Samples and with the requirements of the Work and the Contract Documents.

2. Each submittal shall bear a stamp or specific written indication that CONTRACTOR has satisfied
CONTRACTOR’s obligations under the Contract Documents with respect to CONTRACTOR’s review and
approval of that submittal.

Finance Committee - Agenda - 2/1/2017 - P175

By dnadmin on Mon, 11/07/2022 - 10:28
  • Read more about Finance Committee - Agenda - 2/1/2017 - P175

6.14 Safety Representative

A. CONTRACTOR shall designate a qualified and experienced safety representative at the Site whose duties and
responsibilities shall be the prevention of accidents and the maintaining and supervising of safety precautions and
programs. Work Site is subject to safety inspection by the City Safety Representative at any and all times.

6.15 Hazard Communication Programs

Finance Committee - Agenda - 2/1/2017 - P174

By dnadmin on Mon, 11/07/2022 - 10:28
  • Read more about Finance Committee - Agenda - 2/1/2017 - P174

2. All the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site; and

3. Other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways,
structures, utilities, and Underground Facilities not designated for removal, relocation, or replacement in the
course of construction.