UR EAN DESIGN assocrates Nashua Downtown Master Plan
Phasing of Priority Projects
The priority projects within the first
phase of implementation will include
* Main Street South (Design and
Engineering)
* Bronstein Homes (Design and Hope
VI Application)
* Broad Street Parkway (Design and
Engineering)
+ One Way Street Conversion Study
+ Center for Nashua Heritage and
Future Technology (fundraising)
The priority projects within the second
phase of implementation (years 3-6) will
include:
* Main Street South (begin construc-
tion)
* Broad Street Parkway (begin con-
struction)
* Bronstein Homes (begin construc-
tion)
* Riverfront Parks (design and engi-
neering)
* Performing Arts Center (feasibility
study)
+ Center for Nashua Heritage and
Future Technology (design)
The priority projects within the final
phase of the implementation will
include:
* Riverfront Parks and related develop-
ment projects (construction)
+ Center for Nashua Heritage and
Future Technology
(construction)
* Performing Arts Center
(construction)
Phasing Diagram
Design, Engineering,
Feasibility and
Fundraising for
primary projects
described in the Master
Plan are shown in blue
Primary construction
projects are shown in
red; Phase One : (years
1-3) (tp)
Phase Tuo: (years 3-6}
(middle)
Phase Three: (years 7-
10} (bottom)