THE CITY OF NASHUA
DOWNTOWN PERFORMING ART CENTER
NASHUA, NEW HAMPSHIRE
EXCLUSIONS
EXHIBIT *J”
10/20/2020
The following is a list of exclusions to Harvey Construction’s GMP:
Design Contingency
Recent Tariffs
Construction Testing, Air Quality Testing
Sidewalk closure fee, sidewalk encumbrance fee
Winter Concrete or Masonry
Purchase CADD Files
Purchasing Construction parking spaces
Clerk's Office
Unsuitable soils
Lightweight or Architectural Concrete
Isolated concrete floating floor
Wood Plaza Decking
Roof Davits
Overhead coiling grilles
Metal framed skylight
Exterior Lighted Poster cases
Lath & Plaster
Acoustic Ceiling Tile & Grid
Vertical acoustic operable panels
BDA System
Monitored Fire Extinguishers
Blueprint matched wood paneling
Demountable trap stage floor
Glass shower enclosures
Wall coverings
Grouting or reinforcement of existing masonry
Painted wood base. All base is resilient or tile
Painted concrete
Exterior Paint other than 4-story aluminum window frames, HM exterior doors and
frames and painted terrace rails
Banquet tables or chairs / moveable furniture
Foundation demalition at the 2-story building
SSP6 AESS Prep
Architectural as built in CADD
Design Services
Cost Associated with Special Inspections
Sales Tax
Fire Watch/Temp Fire Pump
Security Watch