Re: Contract for Primary Tank Upgrade Project — Construction Services
NRO § 5-90 (E) states that approval by the Finance Committee of a contract award in excess of
$1,000,000 shall be submitted to the full Board of Aldermen at its next regularly scheduled meeting for
final approval prior to award of the contract.
The Finance Committee approved and placed on file the notification of the award of the
referenced contract at their January 2, 2019 meeting. | am requesting the approval of the full
Board of Aldermen for the award of the following contract, which is over $1,000,000.
Contract for Primary Tank Upgrade Project — Construction Services. Included is the Purchasing
Manager’s Memo #19-103 regarding the award of this contract to the Finance Committee dated
December 27, 2018. This contract total is $3,629,340.
Cc
Sue Lovering, Legislative Affairs Manager
229 Main Street * PO Box 2019 * Nashua, New Hampshire 03061-2019
603.589.3260 * fax 603.594.3450 * NashuaMayor@NashuaNH. gov
www.NashuaNH.gov