PROCESS / SCHEDULE O VERVIEW
OTJ
ARCHITECTS
PHASE DURATION DATES
Existing Conditions
Measuring/Documentation 4 weeks January 16 — February 13, 2019
Programming 4 weeks January 16 — February 13
Schematic Design Phase 8 weeks February 18 — April 12
- Exploratory demolition package
- Cost Estimates/Reconciliation 3 weeks April 15 — May 3
Design Development Phase 12 weeks May 6 — July 26
- Meet with Eversource mid-DD to
discuss rebates Mic-June
- Cost Estimates/Reconciliation 3 weeks July 15 — August 2
Construction Documentation Phase 16 weeks August 5 — November 22
- Demolition/Abatement Package
Demo/Abatement Phase 4 weeks Nov 25 — December 2019
Construction Administration Phase 52 weeks January 2020 — January 2021
ICON
ARCHITECTURE
NASHUA PERFORMING ARTS CENTER
JANUARY 16, 2019