NEXT STEPS / SCHEDULE
DESIGN PHASE DURATION SCHEOULE CONSTRUCTION
PHASE
Existing Conditions 4 weeks January 16 — February 13,
Measuring/Documentation 2019
Programming 4 weeks January 16 — February 13
Schematic Design Phase 3 weeks February 18 - April 12
® Exploratory Demolition ploratory
Package Release Demolition Work
May 2019
« Cost 3 weeks April 15 - May 3
Estimates/Recanciliation
Design Development Phase 12 weeks May 6 - July 26
© Meet with Eversource Mid-June
mid-GD to discuss
rebates oe
« Cost 3 weeks July 15 - August 2 2 py
Estimates/Reconciliation < =
=z @
* Demolitlon/Abatement August 2019 ° a
Package Release E 5
Construction Documentation 16 weeks August 5 —- November 22 5 <=
Phase 5
Dema/Abatement Phase 4 weeks September-October 2019
Construction Administration 52 weeks January 2020 - January Es
Phase 2021 &
NASHUA PERFORMING ARTS CENTER
ICON FEBRUARY 13, 2079