61
Solid Waste Department
DPW Facilities
Comments:
- Major demolition
- New slab on grade
- New exterior walls, siding, MEP systems, sprinkler system
- Total 6,427 SF
- 7-Months
Hard Construction Costs $1,923,280
Design Contingency (20%) $384,656
Architectural, Engineering, Planning (15%) $346,190
Geotechnical Engineering $5,000
Haz-Mat Survey $2,500
Furniture, Fixtures and Equipment $100,000
Owner's Contingency (10%) $276,162
Total $3.037,789*