55
Parks and Recreation Department
DPW Facilities
Comments:
- Demolish 1920's building (1,287 sf)
- New 2-story addition (2,970 SF)
- Renovate 2,440 SF
- Total 5,410 SF
- New HVAC, sprinkler system, flooring, paint, ceilings
- 7-Months
Hard Construction Costs $2,025,282
Design Contingency (20%) $405,056
Architectural, Engineering, Planning (15%) $364,550
Geotechnical Engineering $5,000
Haz-Mat Survey $2,500
Furniture, Fixtures and Equipment $100,000
Owner's Contingency (10%) $290,238
Total $3,192,628*
*Does not include temporary space during
renovations, haz-mat remediation, mold
remediation