Administration
DPW Facilities
Comments:
- 18,376 SF of existing administration and engineering space
- Major renovations to reception area
- New HVAC system, elevator, lighting, fire alarm, sprinkler
modifications, paint, flooring, base
- New roof over Administration and Engineering areas
- 2,200 SF addition (6 offices, conference room, bathrooms)
- Parking lot expansion
- 12-Months
Hard Construction Costs $3,523,260
Design Contingency (20%) $704,652
Architectural, Engineering, Planning (15%) $634,186
Geotechnical Engineering $5,000
Haz-Mat Survey $2,500
Furniture, Fixtures and Equipment $150,000
Owner's Contingency (10%) $501,959
Total $5,521,558*
*Does not include temporary space during
renovations, haz-mat remediation, mold
remediation, structural engineering study