Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Board Of Aldermen - Agenda - 5/24/2016 - P52

Board Of Aldermen - Agenda - 5/24/2016 - P52

By dnadmin on Sun, 11/06/2022 - 21:35
Document Date
Tue, 05/24/2016 - 00:00
Meeting Description
Board Of Aldermen
Document Type
Agenda
Meeting Date
Tue, 05/24/2016 - 00:00
Page Number
52
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/boa_a__052420…

ID ~~ Task Name Duration Start Finish 716 Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017
Oo cones uum vine May dun dub Aug. Sep. Oct. Nov.) Dec. Jan Feb.
Q Nashua, NH SL Conversion Project 155 days Mon 6/13/16 Sun 1/15/17)
1 Contract Award 0 days Mon 6/13/16 Mon6/13/16 @ 6/13
2 Pre-Construction 50 days Mon 6/13/16 Fri 8/19/16 errr
3 Install 3000K fixtures - Trial Period 20 days Mon 6/13/16 Fri 7/8/16
4 Pre-construction meeting 1 day Mon 7/18/16 Mon7/18/16
5 NOTICE TO PROCEED 0 days Tue 7/19/16 Tue 7/19/16 7/19
6 Obtain Permits 10 days Tue 7/19/16 Mon 8/1/16: é
if Material Order and Delivery 6 wks Mon 7/11/16 Fri 8/19/16
a Construction 74 days Tue 8/16/16 Fri 11/25/16 ———EE*
a Mobilization 4 days Tue 8/16/16 Fri 8/19/16 1
10 Crew 1 - Streetlight Fixture Conversion @~120/Wk 9 ewks Fri 8/19/16 Fri 10/21/16:
1) Crew 2 - Streetlight Fixture Conversion @~120/Wk 9 wks Mon 8/22/16 Fri 10/21/16
Crew 3 - Streetlight Fixture Conversion @~120/Wk 9 wks Mon 8/29/16 Fri 10/28/16
X Crew 4 - Streetlight Fixture Conversion @~120/Wk 9 wks Mon 8/29/16 Fri 10/28/16
| 14: Crew 5 - Streetlight Fixture Conversion @~120/Wk 9 wks Mon 9/5/16 Fri 11/4/16.
15 | Punch List creation and clearance 9 wks Mon 9/26/16 Fri 11/25/16
16| Project Close-Out 2idays - Fri1/18/16 —- Fri 12/16/16 =
| 17 | Project Drive-around 1 day Fri 11/18/16 Fri 11/18/16
18 | Project Drive-around 1day Mon11/21/16 Mon 11/21/16
| 19 j Project Acceptance Odays Mon11/28/16 Mon 11/28/16. “@ 11/28
20 Updates in Billing and Rebates 10days Mon11/28/16 —~Fri 12/9/16 al
21 Project Complete - Start of Warranty 0 days Fri12/16/16 =“ Fri 12/16/16. ® 12/16
(22 LDDuration eee 180edays ‘Tue 7/19/16 Sun 1/15/17 >
Task Inactive Summary External Tasks
Split = =a csescceee Manual Task External Milestone
Milestone ¢ Duration-only Deadline
Project: Nashua, NH SL Conversio Summary es Manual Summary Rollup Progress

Date: Thu 5/12/16
Project Summary

Inactive Task

Inactive Milestone

Manual Summary

Start-only
Finish-only

rr

Manual Progress

Page 1

Page Image
Board Of Aldermen - Agenda - 5/24/2016 - P52

Footer menu

  • Contact